Windsor Border Improvements

Project No. 8

Howard Avenue-CPR Grade Separation

Photo of Howard Avenue at the CPR crossing

The CPR mainline crossing on Howard Avenue south of Memorial Drive has caused major traffic delays for the more than 30,000 drivers using Howard Avenue on a daily basis. The implementation of the Vehicle and Cargo Inspection System (VACIS) border screening system has also contributed to these delays, as border-bound trains slow significantly so that their contents can be scanned. Separating the road from the rail line through the construction of a new rail bridge will result in fewer traffic delays and improve traffic flow on this major north-south traffic artery in the city.

Current Project Status

  • The Environmental Assessment and preliminary design study has been completed.
  • Utility relocations, improvements to the detour route, demolition of buildings, and construction of the temporary works have begun.

Next Steps

  • Howard Avenue will be shifted west onto the new detour route in Fall 2009 pending completion of improvements to the detour route and construction of the temporary rail detour.
  • It is anticipated that the new Howard Avenue will reopen to the public by late 2010 with all other work competed by Summer 2011.

Updates

Let's Get Windsor-Essex Moving