This task group identifies MTO requirements for preparing and accepting Hydrology Reports at the different levels of planning and design.
The main objectives of this task group are:
This task group includes the following tasks:
The MTO Regional Structural Section or Bridge Office may alter requirements presented in this document. The drainage practitioner must demonstrate that adverse drainage impacts to the highway right-of-way and upstream/downstream riparian landowners will not occur. The design of the crossing should be based on runoff conditions anticipated 20 years from the time of design, taking full account of present and probable future municipal controls over increases of runoff from new development.
A hydrotechnical study will be required when the design of a new water crossing or a replacement/rehabilitation of an existing structure is being considered. The level of detail of the analysis will vary depending on the level of planning and design being undertaken. In the case of the rehabilitation of structures, if the work being proposed will be above the Highway Water Level and the High Ice Level, a Hydrology Report may not be required. This will have to be confirmed with the MTO project manager.
The level of detail of the analysis will depend on the following:
The Hydrology Report should clearly document the following:
The documentation requirements discussed in this section can be included in the Introduction section of the Hydrology Report. Refer to the section "Organization of the Hydrology Report" for the proposed table of contents of the Hydrology Report.
A number of MTO approvals will be required before the Hydrology Report is finally accepted by MTO. These approvals are:
There is a formal approval process including sign off by the Regional Head of Structural and the Manager of Engineering, for the design criteria and deviations from CHBDC requirements. However, acceptance of the Preliminary and Detailed Hydrology Reports do not require a sign off.
This section should document the following:
At some stage in the planning and design of a water crossing it may be determined that one or more of the requirement set by the CHBDC may not be achieved without significant changes to the approach, surrounding lands or other crossings upstream. In such cases a special approval is required to approve the particular criteria that will not meet the CHBDC requirement. The next section describes the process that is to be followed and the documentation requirements.
The MTO is governed by the CHBDC in the design of bridge and culvert structures and requires that the code requirement be followed in the design of all structure. However, in some cases, due to site conditions, it may be necessary to consider a design option that contravenes a requirement set by the CHBDC. This section specifically addresses two requirements set by the code, namely: the criteria for clearance at the water crossing and freeboard at the approach to a water crossing.
In the event that such deviations are necessary, MTO approvals will have to be sought before the design alternative can be accepted. The approval will be granted by the Manager of Engineering in the region. In some cases concurrence of the Regional Director may be necessary. A justification/ exception report will be required to document the rationale for proposing the deviation.
If a design option that contravenes the CHBDC is being proposed, it is necessary to document the information needed to justify the decision to proceed with such a design. The following information should be included in the report, as a minimum:
To determine the costs associated with the construction of a bridge or culvert, the costs do not only contain the cost of the structure but also the cost of addressing the impact associated with each design alternative. The cost of constructing a bridge or culvert should include the following:
| Welcome | Document Map | About this Document | Quick Reference Guide | Checklists |
| MTO Approvals | Background Information | Drainage Issues | Hydraulic Design |
| Mitigating Impacts | Construction and Operation | Computational Methods |
| MTO Drainage Policy | Glossary | Disclaimer | Authors & Contacts |
This site is maintained by the Government of Ontario
Privacy | Important Notices | External Links Disclaimer
© Queen's Printer for Ontario, 2009
Last modified: January 22, 2009