Before proceeding with the tasks in this grouping, the following tasks should have been completed:
This group of tasks uses all the information and data collected to perform the detailed hydraulic design of the bridge or culvert. The design will take into account the drainage issues identified and provide the design alternative that will address these issues.
The drainage practitioner will complete the following tasks in the group:
The MTO Regional Structural Section or Bridge Office may alter requirements presented in this document. The drainage practitioner must demonstrate that adverse drainage impacts to the highway right-of-way and upstream/downstream riparian landowners will not occur. The design of the crossing should be based on runoff conditions anticipated 20 years from the time of design, taking full account of present and probable future municipal controls over increases of runoff from new development.
This task will outline the hydrologic and hydraulic design criteria for the proposed crossing. These design criteria will have to be approved by the regional engineering office responsible for the project. The regional office should be contacted to determine the approval requirement. It is advisable to acquire the necessary approvals before completing the design of the project.
This section of the report should include a comprehensive list of the design criteria that will govern all the alternatives being considered. These criteria will identify, but are not limited to the following:
To view PDF files, you will require Adobe Acrobat Reader.
The rationale for selection should be included for all the above criteria. Should any design criteria, drainage management policy, guideline or manual of a riparian landowners conflict with a design criteria, drainage management policy, guideline or manual of MTO, or vice versa, a meeting between the parties may be warranted to resolve the conflict.
In order to determine the size of the opening of the bridge or culvert it is essential to determine the flow rate that should be accommodated by the bridge or culvert structure. This flow may be accommodated through the structure as well as allowed to bypass the structure as relief flow. The appropriate means of accommodating the flow should be determined based on MTO Directive B-100, the drainage manual and the Canadian Highway Bridge Design Code and associated exemptions. The hydrologic analysis must be done for, but not limited to the following:
To view PDF files, you will require Adobe Acrobat Reader.
Refer to the section Design Criteria for Highway Drainage Works for more detail.
This section should discuss and document the design flood discharge arrived at, based on the design criteria adopted, and outline the method used in the analysis. Table 8, below gives the information that should be covered in the documentation.
Recognizing that the techniques generally used to arrive at a design flood estimate are statistical in nature and the results may vary with additional data in later years, it is suggested that several methods should be used to verify the results (as outlined in the MTO Drainage Management Manual).
If a stream flow gauging station with a long period of record is available, Single Station Frequency Analysis should be used to derive the design flow rate. The most reliable stream gauge data available from the nearest stream gauging station should be used for Single Station Frequency Analysis. The flow rate data documented in the past by other agencies or in other reports should be used with caution and as a rough estimate only.
If there is no gauging station close to the crossing location or if data is not available, data from other gauging stations on the watercourse can be transposed to the location of the crossing. If such data is not available, data from an adjacent watercourse can be transposed to the crossing location, as long as the two watersheds are hydrologically equivalent. In cases where transposition of the stream flow data is conducted, confirmation of the resulting stream flows, for the different return periods, should be done using other precipitation based hydrologic methods.
If single station frequency analysis is not feasible the use of other methods based on precipitation data must be used. In all cases, method based on precipitation data will be required for the determination of the Regulatory flow rates.
It is ultimately the responsibility of the designer to arrive at the design discharge based on accepted engineering standards and practices, common sense and application of state-of-the-art techniques.
This section should document all the methods used in determining the flow rate and provide the underlying assumptions. Reference to any reports, technical papers, textbooks, and manuals should be provided.
| Computational Analysis | Documentation in Hydrology Report |
|---|---|
| Flow Rate Calculation | Method used, variables, and applicability limitations of the method must be documented. Also, assumptions made have to be stated. |
| Identifying Catchment Inputs | The subsequent values of the different parameters, any method used to calculate these values, and justification for selecting these values must be documented. Also, the assumptions made have to be stated. |
| Selecting Precipitation Data | The type of storm data used: single event (continuous, synthetic, historic, or IDF curves), meteorological station used, and storm duration time step (where applicable) must be documented. Also, the rationale for selecting all of the above and the assumptions made. |
* If any of the methods used have not been included in the MTO Drainage Manual or reviewed in the MTO document "Evaluation of Drainage Software", the Hydrology Report should include a description of the method used and justification for the use of this method on highway projects in Ontario. Based on the location of the project, the applicability of the methods used for Canadian Shield and non-Shield areas should also be confirmed.
The main factor controlling the level of impact of a water crossing structure on the watercourse is the size of the bridge or culvert opening. The smaller the opening the greater the backwater effect in the watercourse upstream of the crossing. At the same time, if the opening is made larger, the span of the structure would be greater and therefore, the cost higher.
The process of establishing the size of the opening starts by assuming an initial size. Once an initial size has been determined, hydraulic analysis will determine the backwater effect. If the backwater effect is unacceptable, according to the design criteria, a new opening configuration is used. Therefore, the process of assessing the proper size of the opening is an iterative one, which is then refined until all the design criteria are met.
There are a number of methods that can be used to determine the size of the opening (s) of the structure. Refer to the sections Bridge Analysis or Culvert Analysis for details of these methods.
The Hydrology Report should provide a complete documentation of the different aspects of the design of the bridge or culvert structure.
The Hydrology Report should document the information listed below. For details on bridge analysis and methods of design refer to the section "Bridge Analysis" and Chapter 5 of the MTO Drainage Management Manual.
If water surface profile software such as HEC-RAS or HEC-2 is used, refer to the section "Minimum documentation requirements"(web link*) in the MTO web document "Evaluation of Drainage Management Software" for details on the minimum information that should be in the Hydrology Report.
The Hydrology Report should document the information listed below. Any special considerations that require a special design should also be included and the resulting design feature documented. For details on culvert analysis and methods of design refer to the section "Culvert Analysis" and to Chapter 5 of the MTO Drainage Management Manual.
If water surface profile software such as CulverMaster is used, refer to the section "Minimum documentation requirements" in the MTO web document "Evaluation of Drainage Management Software" for details.
The Design High Water Level (HWL) estimates should be documented with background information and calculation procedures(s) included in an appendix and briefly described in the body of the report. The Normal Water Levels should also be documented. The definition of these terms is as described in the CHBDC.
According to the CHBDC, there are a number of High Water Levels that need to be determined throughout the design process. These include the following:
Scour is the lowering and/or widening of the streambed due to the erosive forces exerted by flowing water. Channel scour is an important consideration in the design of water crossings as it may undermine the foundations of the structure, possibly leading to its failure. There have been documented failures of structures as a result of scour. Channel scour design requirements are presented in the Drainage Management Manual Chapter 5, in a number of AASHTO publications and in the Canadian Highway Bridge Design Code (CHBDC), 2001.
The following facts should be kept in mind when performing the analysis.
This task should identify the extent of scour, both local and natural, and the resulting decision on the type, depth and location of the bridge footings. The information to be documented should include but is not limited to the following:
The design of a crossing should be checked for the potential impact of ice and debris on the flow through the structure. Ice jams are usually formed during ice break-up and are caused by:
There are two ice-related design aspects that need to be completed in order to determine the required soffit elevation and any training work needed to accommodate the ice flow. These tasks are:
Design ice flow conditions including high ice elevation and the effective thickness of ice floes related to the CHBDC should be estimated and documented based on anticipated discharges and stages.
Where possible, such assessments should be complemented or verified with field data such as ice scars on trees, banks, and historic information based on interviews with long term local residents in the area. This information is valuable for the design of piers and abutments.
If the stream has the potential for jamming due to debris or ice, the implications on the proposed waterway opening should be assessed and documented. This would include assessing the minimum span between piers, span configurations, minimum clearance between the HWL and the soffit. In those cases, historical information gathered from local residents or archives should be included in this discussion.
In situations where ice problems require the construction of ice control device such as weirs, the design of such devices should be provided and their impact on the flow in the watercourse under ice free conditions should be documented.
A regulatory flood is a design flood specified by the Ontario Ministry of Natural Resources for floodplain management purposes. In Ontario, the regulatory flood can be one of the following:
Directive B-100 (PDF - 65 KB) identifies the regions where these regulatory floods apply.
To view PDF files, you will require Adobe Acrobat Reader.
Water crossings should be designed to the design flood frequencies identified in Directive B-100. However, B-100 also states that, "If a drainage facility designed to the criteria specified would increase flooding of buildings or developable land during a regional flood, the facility shall be designed to the regional flood criteria unless otherwise approved. The overall benefit (tangible and intangible) of designing to the regional flood shall be commensurate with the additional cost of the facility, and the proposal should be discussed with the municipality and the landowners adversely affected".
Designing for the regulatory flood could be achieved either through providing for relief flow or by accommodating the regulatory flood through the structure. This will depend on the highway geometrics, the level of service, safety and other considerations. Designing for relief flow means allowing the flow to bypass the main waterway opening and pass over the approach grade or through one or more relief structures. It is generally preferred that the relief flow occur away from the water crossing structure. This would occur by placing the structure away from the road sag. Refer to the MTO Drainage Management Manual for details on locating the structure and relief flow.
Relief flow is beneficial in that it acts as a "safety valve" against bridge or culvert failure in the event of an extreme flood.
The hydraulic analysis providing the water levels under relief and non-relief flow conditions should be documented. The rationale for selecting the best approach should be presented.
If the relief flow option is selected, the path of the relief flow and the impact on adjacent lands and buildings must be documented in the report. The documentation must identify:
| Welcome | Document Map | About this Document | Quick Reference Guide | Checklists |
| MTO Approvals | Background Information | Drainage Issues | Hydraulic Design |
| Mitigating Impacts | Construction and Operation | Computational Methods |
| MTO Drainage Policy | Glossary | Disclaimer | Authors & Contacts |
This site is maintained by the Government of Ontario
Privacy | Important Notices | External Links Disclaimer
© Queen's Printer for Ontario, 2009
Last modified: January 22, 2009