This document is user oriented. MTO documentation requirements are grouped to reflect different stages in the land development planning and design process. Each grouping is subdivided into different tasks that the drainage practitioner may need to undertake. As a result, the user does not have to read the entire document; instead the drainage practitioner only needs to scan the groupings and select the task that is most appropriate. It is the drainage practitioner's responsibility to determine the applicability of the different tasks, and to execute them in an appropriate sequence. Selection of the most appropriate tasks should be based on the suitability to each particular land development proposal, and will depend on the scale and nature of each land development proposal.
Where a proposed land development will be discharging stormwater surface runoff to a receiving drainage system (including the highway drainage system) any potential impacts to the receiving drainage system or the highway drainage system must be examined. When doing so, consider the level of detail required in the analysis.
Since this document is to be used throughout the province, the tasks presented below, and subsequently outlined within the document, must be comprehensive enough to be applicable to the entire range of land development proposals submitted to MTO. Review These Points before Proceeding.
Figure 1: Organization and Sequence of Tasks (Document Map) provides an illustration of MTO drainage requirements as they are subsequently grouped in this document. Figure 1 also presents the tasks that are associated with each grouping.
A brief explanation of the document structure is provided below.
| Issue | Relevance to MTO | |
|---|---|---|
| Status of Land Development Proposal | Preliminary or Detail Stormwater Management Report |
|
| Conformance with the approved land use designations (as per Official Plan or Secondary Plan) |
|
|
| Drainage related Conditions of Approval (i.e. Draft Plan or Site Plan proposals) placed on the proposed land development |
|
|
| Status with other regulatory agencies | ||
| Previous permits issued by MTO for this proponent or for this site |
|
|
| Previous Drainage Studies | Conformance to a previous drainage study (e.g. watershed, subwatershed or master drainage plan, etc.) |
|
| Conformance to previous highway studies (e.g. preliminary design reports) |
|
|
| Need for Water Quality Treatment | Regulatory water quality issues |
|
| Identify Fish Habitat Issues | Regulatory fish habitat requirements* |
|
* Note: The resolution to fish habitat issues is outside the scope of this document. Refer to the MTO Regional Environmental Section, or the appropriate regulatory agency.
| Issue | Relevance to MTO | |
|---|---|---|
| Components | Identify the receiving drainage system |
|
| Obtaining an Outlet | Obtaining an outlet to the highway drainage system |
|
| Regulating Criteria | Identify criteria that will regulate the components of the receiving drainage system (including the highway drainage system) |
|
| Existing Drainage Problems | Identify existing drainage problems on upstream or downstream riparian property |
|
| Identify existing drainage problems on the highway right-of-way |
|
|
| Assessing Impacts to the Receiving Drainage System | Upstream or downstream flooding |
|
| Upstream or downstream erosion problems |
|
|
| Highway flooding |
|
|
| Highway overtopping |
|
|
| Erosion in the highway right-of-way |
|
| Potential Impact to Highway | Relevance to MTO |
|---|---|
| Capacity of highway bridge or highway culvert |
|
| Capacity of highway surface drainage system (roadside ditch, storm sewer, or major system) |
|
| Capacity of highway stormwater management detention facility |
|
| Mitigative Method | Relevance to MTO |
|---|---|
| Stormwater management controls |
|
| Modifications to the receiving drainage system |
|
| Modifications to the highway drainage system |
|
| Erosion protection works |
|
| Issue | Relevance to MTO |
|---|---|
| Sediment and erosion control during construction |
|
| Operation and maintenance responsibilities, and ownership of the drainage works |
|
| Welcome | Document Map | About this Document | Quick Reference Guide | Checklist |
| MTO Approvals | Drainage Issues | Drainage Impacts | Capacity | Mitigating Impacts |
| Construction and Operation | Computational Methods | MTO Drainage Policy | Glossary |
| Disclaimer | Authors & Contacts |