Southern Highways Program
2008 to 2012

Expansion Projects

Golden Horseshoe Expansion 2008 to 2012

list of 2008 highway expansion projects, in PDF format

The list of projects is organized by region, highway, and location. Each project is accompanied by a brief description.

(Alternatively, a project list in PDF format is also available.)

NOTE: Project timing is subject to change based on funding, planning, design, environmental approval, property acquisition and construction requirements.

Each project is numbered, to identify its location on this map of the Greater Golden Horseshoe.

map of Greater Golden Horseshoe, indicating locations of highway expansion projects

For details about each project, click on the numbers which appear on the above map (then press the "back" button on your browser, to return to this map.)

Central Ontario

Highway 7
Map #1: Brock Road, Pickering to Highway 12, Brooklin (FLOW)
Two to four lane widening
planned/expected start: 2010, planned/expected completion: 2012
Highway 10
Map #2: Caledon to Highway 9 - Phase 1 of 2 - 1 km north of Regional Road 24 to Highway 9
Two to four lane widening
planned/expected start: underway, planned/expected completion: 2009
Map #3: Caledon to Higway 9 - Phase 2 of 2 - 1 km south of Regional Road 24 to 1 km north of Regional Road 24
Two to four lane widening
planned/expected start: 2008, planned/expected completion: 2009
Highway 26N
Map #4: Wasaga to Collingwood - Phase 2 of 3 - Fairgrounds Road and Batteaux River Bridges
New bridges
planned/expected start: underway, planned/expected completion: 2008
Map #5: Wasaga to Collingwood - Phase 3 of 3 - Sixth line to existing Highway 26
New four-lane highway
planned/expected start: 2009, planned/expected completion: 2010
Highway 400
Map #6: King Road interchange, York Region (High Occupancy Vehicle lanes)
Interchange improvement
planned/expected start: 2008, planned/expected completion: 2010
Map #7: Major MacKenzie Drive to King Road, Vaughan (High Occupancy Vehicle lanes)
Six to eight lane widening
planned/expected start: 2010, planned/expected completion: 2012
Map #8: Teston Rd, Vaughan (partnership with York Region)
New interchange
planned/expected start: underway, planned/expected completion: 2008
Map #9: Essa Road interchange, Barrie (High Occupancy Vehicle lanes)
New commuter parking lot
planned/expected start: underway, planned/expected completion: 2008
Highway 401
Map #10: Stevenson Road to Highway 35/115 split & Stevenson Road interchange, Oshawa
Resurfacing/new interchange
planned/expected start: underway, planned/expected completion: 2010
Map #11: McLaughlin Road bridge, Mississauga (partnership with City of Mississauga)
Bridge replacement
planned/expected start: 2008, planned/expected completion: 2008
Map #12: Highway 410 to Hurontario Street, Mississauga
New interchange/widening
planned/expected start: 2009, planned/expected completion: 2012
Map #13: Highway 410 to Hurontario Street, Mississauga
New patrol yard
planned/expected start: 2008, planned/expected completion: 2010
Highway 403
Map #14: Waterdown Road interchange (partnership with the City of Burlington)
Upgrade to full interchange
planned/expected start: 2008, planned/expected completion: 2009
Map #15: Winston Churchill Boulevard, Mississauga (High Occupancy Vehicle lanes)
New commuter parking lot
planned/expected start: 2009, planned/expected completion: 2009
Map #16: Erin Mills Parkway, Mississauga (High Occupancy Vehicle lanes)
New commuter parking lot
planned/expected start: 2009, planned/expected completion: 2009
Highway 404
Map #17: Highway 404 Extension - Phase 1 of 4 - Green Lane overpass, York Region (FLOW)
New bridge
planned/expected start: underway, planned/expected completion: 2008
Map #18: Highway 404 Extension - Phase 2 of 4 - Mount Albert Road, overpass, York Region (FLOW)
New bridge
planned/expected start: 2008, planned/expected completion: 2009
Map #19: Highway 404 Extension - Phase 3 of 4 - Green Lane to Queensville Side Road, York Region (FLOW)
New four-lane highway
planned/expected start: 2010, planned/expected completion: 2012
Map #20: Highway 404 Extension - Phase 4 of 4 - Queensville Side Road to Ravenshoe Road, York Region (FLOW)
New four-lane highway
planned/expected start: 2010, planned/expected completion: Beyond 2012
Map #21: Aurora Road interchange, Aurora (High Occupancy Vehicle lanes)
New commuter parking lot
planned/expected start: underway, planned/expected completion: 2008
Highway 410
Map #22: Bovaird Drive to Mayfield Road, Brampton
New four-lane highway
planned/expected start: underway, planned/expected completion: 2008
Map #23: Mayfield Road to Highway 10, Brampton
New four-lane highway
planned/expected start: underway, planned/expected completion: 2009
Highway 427
Map #24: Highway 409 to Highway 407, Toronto (High Occupancy Vehicle lanes)
Widening
planned/expected start: 2010, planned/expected completion: 2012
QEW
Map #25: Seventh Street to Garden City Skyway, St. Catharines (Border Infrastructure Fund)
Four to six lane widening
planned/expected start: underway, planned/expected completion: 2011
Map #26: Red Hill Valley Parkway interchange - Phase 3 of 3 - connection to QEW, Hamilton
New interchange & widening
planned/expected start: underway, planned/expected completion: 2009
Map #27: Burloak Drive to Third Line, Oakville (High Occupancy Vehicle lanes)
Six to eight lane widening
planned/expected start: underway, planned/expected completion: 2011
Map #28: Third Line to Trafalgar Road, Oakville (High Occupancy Vehicle lanes)
Six to eight lane widening
planned/expected start: underway, planned/expected completion: 2011
Map #29: Guelph Line to Burloak Drive, Burlington/Oakville (High Occupancy Vehicle lanes)
Six to eight lane widening
planned/expected start: 2009, planned/expected completion: 2011

Eastern Region

Highway 7
Map #30: Highway 28 to Drummond Line, Peterborough
Two to five lane widening
planned/expected start: 2008, planned/expected completion: 2010
Map #31: Lindsay Bypass - Victoria Cty. Road 36 to Angeline Street and Highway 35 from Highway 7 southerly 2.2 km
Two to four and four to five lane widening
planned/expected start: 2010, planned/expected completion: 2012

Southwestern Ontario

Highway 8
Map #32: Kitchener - Waterloo Expressway - Grand River to Sportsworld Drive
Four to six & six to eight lane widening
planned/expected start: 2009, planned/expected completion: 2011
Highway 401
Map #33: Woodstock to Cambridge - Phase 1 of 3 - Drumbo Road to Waterloo Road 97 (Cedar Creek Road)
Four to six lane widening
planned/expected start: underway, planned/expected completion: 2008
Map #34: Woodstock to Cambridge - Phase 3 of 3 - Oxford Road 2 to Drumbo Road
Four to six lane widening
planned/expected start: 2008, planned/expected completion: 2011