Eastern Ontario Rehabilitation 2008

list of Eastern Ontario 2008 highway rehabilitation projects, in PDF format

The list of projects is organized by highway and location. Each project is accompanied by a brief description.

(Alternatively, a project list in PDF format is also available.)

NOTE: Project timing is subject to change based on funding, planning, design, environmental approval, property acquisition and construction requirements.

Each project is numbered, to identify its location on this map of Southern Ontario.

map of Eastern Ontario region, indicating locations of 2008 highway rehabilitation projects

For details about each project, click on the numbers which appear on the above map (then press the "back" button on your browser, to return to this map.)

Highway 7
Map #1: Drummond Line to Peterborough
Resurfacing/left turn lane
status: underway, planned/expected completion: 2009, project length: 3 km
Map #2: West of Highway 62 to Marmora
Resurfacing/passing lanes
status: underway, planned/expected completion: 2008, project length: 12 km
Map #3: Lennox and Addington/ Hastings Cty. Line to Highway 37
Resurfacing/passing lane
status: new, planned/expected completion: 2009, project length: 8 km
Map #4: Norwood, east to west limits
Resurfacing
status: new, planned/expected completion: 2009, project length: 2 km
Highway 7A
Map #5: Bethany Creek Bridge, Bethany
Bridge rehabilitation
status: new, planned/expected completion: 2008, project length: n/a
Highway 15
Map #6: Smiths Falls to Lanark Road 10
Reconstruction/passing lanes
status: underway, planned/expected completion: 2008, project length: 14 km
Highway 17
Map #7: Constable Philip Shrive and CPR overhead, Renfrew
Bridge rehabilitation
status: new, planned/expected completion: 2010, project length: n/a
Map #8: Renfrew Road 508 to Renfrew
Resurfacing
status: new, planned/expected completion: 2008, project length: 12 km
Map #9: Renfrew Road 40 to Renfrew Road 24, Pembroke
Resurfacing/intersection improvements
status: new, planned/expected completion: 2008, project length: 6 km
Map #10: Renfrew Road 20 to Storyland, Renfrew
Resurfacing
status: new, planned/expected completion: 2008, project length: 5 km
Highway 28
Map #11: Young's Point Road to Burleigh Falls
Resurfacing
status: new, planned/expected completion: 2009, project length: 9 km
Map #12: Bancroft to Hardwood Lake
Resurfacing
status: new, planned/expected completion: 2008, project length: 35 km
Highway 33
Map #13: Prince Edward Road 1, west of Picton
Intersection improvements
status: new, planned/expected completion: 2009, project length: n/a
Map #14: Speers Boulevard, Amherstview
Intersection improvements
status: new, planned/expected completion: 2009, project length: n/a
Highway 34
Map #15: Hawkesbury Creek / OCR Bridge, Hawkesbury
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #16: Vankleek Hill to Green Lane Road
Resurfacing
status: new, planned/expected completion: 2009, project length: 6 km
Highway 35
Map #17: Victoria Road 4, Lindsay
Intersection improvements
status: underway, planned/expected completion: 2008, project length: n/a
Highway 37
Map #18: CNR overhead, north of Belleville
Bridge rehabilitation
status: new, planned/expected completion: 2008, project length: n/a
Highway 41
Map #19: Bon Echo Park to Machesney Lake Road, Bon Echo
Resurfacing
status: underway, planned/expected completion: 2008, project length: 7 km
Map #20: Cloyne to Bon Echo Park
Resurfacing
status: new, planned/expected completion: 2009, project length: 14 km
Highway 49
Map #21: Hastings Road 2, Deseronto
Traffic signals
status: underway, planned/expected completion: 2008, project length: n/a
Highway 60
Map #22: Kearney and Headstone Bridges, Whitney
Bridge replacements
status: new, planned/expected completion: 2008, project length: n/a
Map #23: Deacon to Golden Lake
Resurfacing
status: new, planned/expected completion: 2008, project length: 8 km
Highway 115
Map #24: Highway 35 to Peterborough Road 10
Reconstruction/paved shoulders
status: new, planned/expected completion: 2008, project length: 23 km
Highway 118
Map #25: West Junction of Haliburton Road 648 to east Junction 648, west of Bancroft
Resurfacing
status: new, planned/expected completion: 2008, project length: 12 km
Highway 401
Map #26: Pitt Street to Brookdale Avenue, Cornwall
Noise barriers
status: new, planned/expected completion: 2008, project length: 1 km
Map #27: Northumberland Road 30, Brighton
Interchange improvement
status: new, planned/expected completion: 2008, project length: n/a
Map #28: Lennox and Addington Road 4 underpass (interchange 593), Kingston
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #29: Ivy Lea border crossing
Queue end warning system
status: new, planned/expected completion: 2008, project length: n/a
Map #30: Gananoque River Bridge, Gananoque
Bridge painting
status: new, planned/expected completion: 2009, project length: n/a
Map #31: Trent River Bridge overpass, Trenton
Bridge rehabilitation/widening
status: new, planned/expected completion: 2012, project length: n/a
Map #32: Upper Canada Road to Carman Road, Morrisburg
Resurfacing
status: new, planned/expected completion: 2009, project length: 21 km
Map #33: Boundary Road to Moulinette Road, westbound lane, Cornwall
Resurfacing
status: new, planned/expected completion: 2008, project length: 18 km
Map #34: Deer Park Road underpass, Port Hope
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #35: Newburgh Road underpass, Napanee
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #36: Cranberry Road underpass, Port Hope
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Highway 416
Map #37: Barnes Creek, south Kemptville
Culvert replacement
status: new, planned/expected completion: 2009, project length: n/a
Highway 417
Map #38: County Road 23 underpass near Dalkeith
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #39: East Hawkesbury Township Road underpass
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Map #40: Highway 17 underpass (interchange 9)
Bridge rehabilitation
status: new, planned/expected completion: 2009, project length: n/a
Highway 115
Map #41: Peterborough Road 28 overpass - northbound, and Highway 115 southbound exit ramp at Highway 7, Springville
Bridge rehabilitation/ramp improvements
status: new, planned/expected completion: 2009, project length: n/a