Quick Facts
Highway 400/69 Corridor (# of vehicles) |
||
Average Volume Based on 2004 Data |
Port Severn - |
Parry Sound - |
Average Daily Traffic Volume Ranges |
7,400 to 12,200 |
5,300 to 11,500 |
Summer Daily Average Volume Ranges |
13,700 to 20,500 |
7,750 to 15,500 |
Average Daily Truck Volume Ranges |
926 to 3,280 |
860 to 2,820 |
Four Laning - Muskoka Road 32/38 to Parry Sound Area (Seguin River)
- Distance 52 km
- 14 km - Twinning (build 2 new lanes parallel to existing highway and convert to 4 lanes)
- 38 km - New Alignment (build all new 4 lanes, by-passing existing highway)
- New by-passes constructed around the communities of Parry Sound and MacTier
- Over 90 properties have been acquired
- 10 new interchanges
- 36 new bridges
- 6.3 million cubic metres of rock excavation, about four times the volume of the Rogers Centre (SkyDome)
- 1.6 million cubic metres of earth excavation
- 2.8 million tonnes of granular material
- 480,000 tonnes of asphalt
Four Laning - Parry Sound (Seguin River) to Sudbury
- Distance 152 km
- Estimated project features:
- 20 interchanges
- 103 bridges
- 14 river crossings
- 50 stream crossings
- 37 million cubic metres of materials to be moved (22 times the volume of the Rogers Centre (SkyDome)), including:
- 23 million cubic metres of rock excavation
- 7 million cubic metres of earth excavation
- 8.4 million tonnes of granular material
- 1.3 million tonnes of asphalt
- 40,000 machine hours of swamp excavation (5,000 person days of work)
- New bypasses around communities as needed
- Access to new four-lane highway via interchanges
- Service road network
- 30 metre median will separate north and south bound lanes
- Route will be a combination of:
- two new lanes to twin the existing highway
- four new lanes on new alignment
- 17 km from Parry Sound (Seguin River) to Highway 559
- route planning completed
- construction is underway on 2 separate projects in this section
- From 3.5 km South of Highway 124 to the South Limit of the Town of Nobel – 7km
- From the South Limit of the Town of Nobel Northerly – 5 km
- detail design and property acquisition is complete for the remaining 5 km and construction is scheduled to begin in 2008.
- 41 km from Highway 559 Northerly
- route planning is completed
- Detail Design and property acquisition is underway on three separate projects:
- From 3.5 km North of Highway 559 to 1 km North of Highway 7182 (Shebeshekong Road) – 16 km
- From 0.4 km North of Highway 7182 (Shebeshekong Road) to the South Junction of Highway 529 – 11 km
- From the South Junction of Highway 529 to Harris Lake Road – 14 km
- 27 km from Harris Lake Road Northerly
- Route planning is currently underway and expected to be completed in 2008
- 47 km from Highway 522 to Estaire
- route planning completed
- engineering and property acquisition has begun in two sections:
- Highway 522 to Highway 64 - 25 km
- Highway 64 to Estaire - 22 km
- 19.2 km from Estaire to Sudbury
- route planning completed
- construction underway on three separate projects in this section:
- Highway 537 to Sudbury - 8.6 km
- Estaire to Highway 537 - 4.1 km
- Estaire bypass - 6.5km
- engineering and property acquisition underway for the final project in this section to open the new highway from Estaire to Highway 537