Status of Construction Activity
A: Recently Completed Projects |
||
Location |
Length |
Date Opened |
Muskoka 32/38 to Musquash River |
4 km |
October 1999 |
Badger Road to Seguin River (Parry Sound Bypass) |
10 km |
November 2001 |
Highway 141 to Badger Road |
4 km |
October 2002 |
MacTier to Highway 141 |
26 km |
October 2003 |
Interchange at Muskoka Roads 32 and 38 |
-- |
October 2005 |
Interchange at Gladu Road |
2.4 km |
Completed June 2006 (to be opened with Highway 537 to Sudbury) |
Old Wanup Road underpass |
0.6 km |
Completed July 2006 (to be opened with Highway 537 to Sudbury) |
B: Projects Currently Under Construction |
||
Location |
Length |
Planned Opening Date |
Musquash River to MacTier. Construction started December 2004 |
8 km |
Summer 2008 |
Parry Sound to Nobel. Construction started June 2005 |
7 km |
2010 |
Nobel Bypass. Construction started October 2006 |
5 km |
2010 |
Highway 537 to Sudbury (three separate contracts). Construction started January 2005. |
8.6 km |
2009 |
Estaire to Highway 537. Construction started January 2007 |
4.1 km |
2010 |
Estaire Bypass. Construction started September 2006 |
6.5 km |
2010 |
C: Projects Currently In Planning / Engineering / Property Acquisition |
|
Location |
Length |
From North of Nobel to Highway 559 |
5 km |
From Highway 559 to Highway 7182 (Shebeshekong Road) |
16 km |
From Highway 7182 (Shebeshekong Road) to the South Junction Highway 529 |
11 km |
From the South Junction Highway 529 to Harris Lake Road |
14 km |
From Harris Lake Road to Highway 522 |
27 km |
Highway 522 to Highway 64 |
25 km |
Highway 64 to Estaire |
22 km |