Status of Construction Activity

A: Recently Completed Projects
Location Length Date Opened
Muskoka 32/38 to Musquash River 4 km October 1999
Badger Road to Seguin River (Parry Sound Bypass) 10 km November 2001
Highway 141 to Badger Road 4 km October 2002
MacTier to Highway 141 26 km October 2003
Interchange at Muskoka Roads 32 and 38 -- October 2005
Interchange at Gladu Road 2.4 km Completed June 2006 (to be opened with Highway 537 to Sudbury)
Old Wanup Road underpass 0.6 km Completed July 2006 (to be opened with Highway 537 to Sudbury)

B: Projects Currently Under Construction
Location Length Date Opened
Musquash River to MacTier. Construction started December 2004 8 km Summer 2008
Parry Sound to Nobel. Construction started June 2005 7 km 2010
Nobel Bypass.  Construction started October 2006 5 km 2010
Highway 537 to Sudbury (three separate contracts). Construction started January 2005. 8.6 km 2009
Estaire to Highway 537.  Construction started January 2007 4.1  km 2010
Estaire Bypass.  Construction started September 2006 6.5  km 2010

C: Projects Currently In Planning / Engineering / Property Acquisition
Location Length
From North of Nobel to Highway 559 5 km
From Highway 559 to Highway 7182 (Shebeshekong Road) 16 km
From Highway 7182 (Shebeshekong Road) to the South Junction Highway 529 11 km
From the South Junction Highway 529 to Harris Lake Road 14 km
From Harris Lake Road to Highway 522 27 km
Highway 522 to Highway 64 25 km
Highway 64 to Estaire 22 km