Construction Reports: Northeastern

Contract #: 2016-5143
Start of Construction : June 20, 2016
Estimated End of Construction : June 27, 2017
Highway : 144
Length of Construction : 11.60 km
Close To : Chelmsford
Type of Contract : Structural Culvert replacement, Grading, Drainage, Granular Base, Hot Mix Paving.
Value of Contract : $9,564,393.00
Description : Highway 144: 0.5 kilometres North of Municipal Road 12, Northerly 11.6 kilometres to 1.5 kilometres South of Municipal Road 8 for 11.6 kilometres, includes Culvert Replacement, 15.1 kilometres north of Municipal Road 15. Work includes Grading, Drainage, Granular Base, Hot Mix Paving, Electrical, and Structural Culvert Replacement.
Traffic Impact : Highway 144, 0.5 kilometres north of Municipal Road 12. Northerly for 11.6 kilometres to 2.5 kilometres south of Regional Road 8. There is no impact on traffic. Work has shut down for the season and will resume in the spring of 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5133
Start of Construction : May 16, 2016
Estimated End of Construction : June 30, 2017
Highway : 654
Length of Construction : 22.70 km
Close To : Callander
Type of Contract : Grading, drainage, granular base, warm mix paving, electrical and structural. Stage #2 Structure Rehabilitation
Value of Contract : $11,447,040.00
Description : Work includes grading, drainage, milling and paving, Also include repairs and rehabilitation to Wasi River Bridge, South River Bridge and Bear Creek Bridge.
Traffic Impact : On Highway 654, from Highway 534 easterly to Highway 11 for 22.7 kilometres. There is no impact on traffic. Work completed for the winter months, will resume in the spring of 2017
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5131
Start of Construction : June 08, 2016
Estimated End of Construction : November 30, 2017
Highway : 17
Length of Construction : 21.50 km
Close To : Spanish
Type of Contract : Resurfacing and Bridge Rehabilitation
Value of Contract : $19,431,250.00
Description : Work includes Grading, Drainage,Granular Base, Hot Mix Paving, Electrical and Structural.
Traffic Impact : Spanish River Bridge, Highway 17, from 3.5 kilometres West of Highway 6 Easterly 18.8 kilometres to Nairn Centre, and Highway 6 from Highway 17 Southerly 2.7 kilometres. There is no impact on traffic. Work shut down for the winter months, will resume April 10, 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5131
Start of Construction : June 08, 2016
Estimated End of Construction : November 30, 2017
Highway : 6
Length of Construction : 21.50 km
Close To : Spanish
Type of Contract : Resurfacing and Bridge Rehabilitation
Value of Contract : $19,431,250.00
Description : Work includes Grading, Drainage,Granular Base, Hot Mix Paving, Electrical and Structural.
Traffic Impact : Spanish River Bridge, Highway 17, from 3.5 kilometres West of Highway 6 Easterly 18.8 kilometres to Nairn Centre, and Highway 6 from Highway 17 Southerly 2.7 kilometres. There is no impact on traffic. Work shut down for the winter months, will resume April 10, 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5130
Start of Construction : May 23, 2016
Estimated End of Construction : June 20, 2017
Highway : 17
Length of Construction : 22.20 km
Close To : Sudbury
Type of Contract : Road Rehabilitation
Value of Contract : $12,508,400.00
Description : Work includes Grading, Drainage, Granular Base, Hot Mix Paving, Structural and Electrical.
Traffic Impact : Highway 17, from 1.2 kilometres east of Sudbury at Highway 17 & Municipal Road 55 intersection westerly on 17 for 21 kilometres. There is no impact on traffic. Work stopped for the winter months, will resume in the spring of 2017
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5129
Start of Construction : July 04, 2016
Estimated End of Construction : October 27, 2017
Highway : 11
Length of Construction : 34.70 km
Close To : Val Rita
Type of Contract :
Value of Contract : $29,174,493.00
Description : Work includes Grading Drainage, Granular Base, Hot Mix Paving, Electrical, Structural Culvert Replacement and Structural Rehabilitation: Solomon Creek Bridge Rehab, 45.7 kilometres west of Highway 581, Holledge Creek Culvert Rehab, 51.5 kilometres west of Highway 581, (8.3 kilometres east of Opasatika River Bridge) East of Opasatika, and Creek Culvert Replacement, 3.3 kilometres east of Opasatika River Bridge.
Traffic Impact : Resurfacing Highway 11, 200 metres west of Hyundai Road easterly for 34.7 kilometres. (42 kilometres west of Kapuskasing). There is no impact on traffic. Highway is unobstructed. Work on hold for winter months. Will resume in spring 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5127
Start of Construction : June 20, 2016
Estimated End of Construction : October 05, 2018
Highway : 11
Length of Construction : 0.00 km
Close To : Nagagami
Type of Contract : Grading, Drainage, granular Base, Hot Mix Paving, Electrical and Structure replacement.
Value of Contract : $27,883,565.00
Description : Highway 11 : Nagagami River Bridge Replacement, 2.1 kilometres west of highway 631 and Shekak River Bridge Replacement, 9.4 kilometres east of Highway 631 for 3.3 kilometres.
Traffic Impact : Highway 11 Nagagami and Shekak River Bridges. There is no impact on traffic. All restrictions lifted, no reduced speeds or closures. Off road work at this time.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5010
Start of Construction : June 13, 2016
Estimated End of Construction : May 31, 2017
Highway : 400
Length of Construction : 9.50 km
Close To : MacTier
Type of Contract : Resurfacing
Value of Contract : $9,718,985.00
Description : Work includes Grading, Hot Mix Paving, Resurfacing and Fence Installation.
Traffic Impact : Highway 400 northbound and southbound lanes, preventive resurfacing from 2.9 kilometres north of Muskoka Road 12 northerly to Healy Lake Road Underpass for 9.5 kilometres. From 1.4 kilometres north of Muskoka Road in the Township of Gibson Northerly to 1.0 kilometres North of Healy Lake Road Underpass, in the Township of Conger. Expect delays up to 5 minutes. Traffic will encounter daily single lane (lane 1 or lane 2 depending on the contractor's operation) closures throughout the project (9.5 kilometers) on Highway 400 northbound and southbound during week days. Lane closures are subject to weather condition, planned operations and AMC snow ploughing operation schedule. No speed reduction during lane closures. Traffic delineated by traffic control barrel-open lane width is 3.5 meters, median shoulder width varies 1 meter to 1.5 meters. Other shoulder width varies 3 meters to 3.5 meters. No reduced height.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5008
Start of Construction : June 24, 2016
Estimated End of Construction : July 31, 2017
Highway : 141
Length of Construction : 0.20 km
Close To : Rosseau
Type of Contract : Structure replacement
Value of Contract : $3,229,063.95
Description : Replacement of Rosseau River structure.
Traffic Impact : On Highway 141, 5.9 kilometres east of Highway 632. Rosseau River Bridge. There is no impact on traffic. Single lane over the bridge will remain for the winter months. Work will shut down for the winter , Will resume in April 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5007
Start of Construction : May 24, 2016
Estimated End of Construction : October 11, 2017
Highway : 11
Length of Construction : 0.00 km
Close To : Bracebridge
Type of Contract : Structure Rehabilitation
Value of Contract : $4,342,899.00
Description : Highway 11 Vankoughnet Road Underpass Rehabilitation at Highway 118, and Taylor Road Underpass Rehabilitation, 3.9 kilometres south of Muskoka Road 117 at Bracebridge, for 0.8 kilometres. Work includes grading, granular base, hot mix paving, drainage, electrical and structural.
Traffic Impact : 0.5 Kilometers South of Highway 118, 2 kilometers North of Road Underpass. There is no impact on traffic. Work completed for the winter months, will resume in the spring of 2017
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2016-5007
Start of Construction : May 24, 2016
Estimated End of Construction : October 11, 2017
Highway : 118
Length of Construction : 0.00 km
Close To : Muskoka Falls
Type of Contract : Structure Rehabilitation
Value of Contract : $4,342,899.00
Description : Highway 11 Vankoughnet Road Underpass Rehabilitation at Highway 118, and Taylor Road Underpass Rehabilitation, 3.9 kilometres south of Muskoka Road 117 at Bracebridge, for 0.8 kilometres. Work includes grading, granular base, hot mix paving, drainage, electrical and structural.
Traffic Impact : Vankoughnet Road Underpass. There is no impact on traffic. Work completed for the winter months, will resume in the spring of 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5128
Start of Construction : February 29, 2016
Estimated End of Construction : August 31, 2017
Highway : 540
Length of Construction : 17.50 km
Close To :
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical, Structural Culvert Rehabilitation, Structural Culvert Replacement and Bridge Replacement
Value of Contract : $13,127,126.00
Description : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Replacement & Rehabilitation. Includes 2 structural culverts rehabilitations, 3 structural culvert replacements and one bridge replacement.
Traffic Impact : Close to Kagawong on Highway 540 westerly for 16.0 kilometres and Highway 540 B from Highway 540/542 junction northerly for 1.0 kilometre. Highway 540, 12.0 kilometres west of Highway 6/540 junction. Expect delays up to 5 minutes. One lane closure restriction for scheduled operations at Kagawong Bridge. For 1 lane restriction temporary traffic light installed at Kagawong Bridge.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5126
Start of Construction : November 09, 2015
Estimated End of Construction : October 20, 2017
Highway : 11
Length of Construction : 4.80 km
Close To : Powassan
Type of Contract : GRADING, DRAINAGE, GRANULAR BASE, HOT MIX PAVING, PARTIAL ILLUMINATION AND STRUCTURES
Value of Contract : $22,796,025.00
Description : Rehabilitation of Highway 11 Northbound lanes from 5.7 kilometres south of Highway 534 Interchange northerly 4.8 km, Grading, Drainage, Granular Base, Hot Mix Paving and Structures - New North McGillvray Creek Bridge (NBL), 3.8 kilometres south of highway 534/Clarke Street Interchange, Culvert Replacement with New Br and McGillvray Creek Tributary Culvert (NBL) Replacement and SBL Rehabilitation Ext, 1.9 kilometres south of highway 534/Clarke Street Interchange, 1&2 two New Snowmobile Culverts northbound and southbound lanes.
Traffic Impact : 5.7 kilometres south of Highway 534, northerly for 4,8 kilometres, municipality of Powassan - 5,6 kilometres. There is no impact on traffic. All restrictions lifted. Work completed for the winter months. Work will resume in the spring of 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5121
Start of Construction : September 08, 2015
Estimated End of Construction : October 06, 2017
Highway : 66
Length of Construction : 3.40 km
Close To :
Type of Contract : Realignment of Highway and Surface Rehabilitation. Grading, Drainage, Granular Base, Hot mix Paving and Electrical
Value of Contract : $22,087,577.00
Description : Work includes Grading, Granular Base, Hot Mix Paving and Electrical (Illumination).
Traffic Impact : Near Virginiatown, from 10.6 kilometres east of Highway 624 easterly for 3.4 kilometres. There is no impact on traffic. Speed limit restrictions lifted. Work shutdown for winter months, will resume in the spring of 2017
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5119
Start of Construction : January 03, 2016
Estimated End of Construction : September 30, 2020
Highway : 69
Length of Construction : 14.90 km
Close To : French River
Type of Contract : 4 lane expansion INCLUDING GRADING, DRAINAGE, GRANULAR BASE, HOTMIX PAVING, ELECTIRCAL AND STRUCTURAL WORK .
Value of Contract : $197,303,069.00
Description : Work includes 14.9 kilometres of mainline construction, 2 full interchanges, 10 new bridges, mulltiple structural culverts, Electrical - illumination and counting stations, relocation of Variable Message Signs.
Traffic Impact : Near French River, from 2.9 kilometres north of Highway 522 to 4.6 kilometres north of Highway 607 for 14.9 kilometres. Expect delays up to 15 minutes. Speed limit reduced to 70 kilometers per hour when workers are present until September 2020. Speed reduction zone extends the whole contract where required (ie flagging operations usually for blasting). Passing lanes both North and South bound on existing Highway 69 closed to one lane in each direction for the duration of contract
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5115
Start of Construction : May 09, 2016
Estimated End of Construction : October 17, 2017
Highway : 101
Length of Construction : 32.60 km
Close To : Wawa
Type of Contract : Grading, Drainage, Granular, Hot Mix Paving, Electrical, and Structure Rehabilitation
Value of Contract : $28,451,187.00
Description : Rehabilitation of Highway 17 from 14.8 kilometres north of Highway 101 southerly for 30.4 kilometres and rehabilitation of Speckled Trout Creek Culvert and Agawa River Overflow Culverts on Highway 17, 85 kilometres south of Highway 101.
Traffic Impact : Highway 17, 14.8 kilometres north of Highway 101 for 30.4 kilometres. There is no impact on traffic. All restrictions lifted, work stopped for the winter months, will resume in May 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5115
Start of Construction : May 09, 2016
Estimated End of Construction : October 17, 2017
Highway : 17
Length of Construction : 32.60 km
Close To : Wawa
Type of Contract : Grading, Drainage, Granular, Hot Mix Paving, Electrical, and Structure Rehabilitation
Value of Contract : $28,451,187.00
Description : Rehabilitation of Highway 17 from 14.8 kilometres north of Highway 101 southerly for 30.4 kilometres and rehabilitation of Speckled Trout Creek Culvert and Agawa River Overflow Culverts on Highway 17, 85 kilometres south of Highway 101.
Traffic Impact : Highway 17, 14.8 kilometres north of Highway 101 for 30.4 kilometres. There is no impact on traffic. All restrictions lifted, work stopped for the winter months, will resume in May 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5100
Start of Construction : June 29, 2015
Estimated End of Construction : May 30, 2017
Highway : 69
Length of Construction : 0.76 km
Close To :
Type of Contract : Highway four lane expansion.
Value of Contract : $23,373,204.00
Description : Work includes grading, drainage, granular base, hot mix paving and structures. Construction of 2.7 kilometres of realigned railway tracks; and 0.6 kilometres of new Highway 69 north and southbound lanes from 1.2 kilometres south of existing Highway 522.
Traffic Impact : On Highway 69,1.2 kilometres south of Highway 522, for 0.76 kilometres northerly. There is no impact on traffic. The Existing Highway 69 Realignment has been reopened with a 90 kilometers per hour speed limit. Work shut down for the winter months, will resume in the spring of 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5006
Start of Construction : December 14, 2015
Estimated End of Construction : November 30, 2017
Highway : 11
Length of Construction : 12.00 km
Close To :
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Culvert Replacement
Value of Contract : $17,205,350.00
Description : Design Build Minor, Rehabilitation of Highway 11 (NBL's & SBL's) from north of North Muskoka Road Bridge to South Mary Lake Road for 12.0 kilometres, including Unknown Culvert Rehabilittion, 0.9 kilometres north of Stephenson Road 1.
Traffic Impact : Highway 11 North of North Muskoka River Bridge to South Mary Lake Road for 12.0 kilometres. There is no impact on traffic. Possible mobile single lane closures, very short duration single lane closures. No speed reduction. No lane width restriction. No reduced height
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2015-5004
Start of Construction : June 22, 2015
Estimated End of Construction : June 16, 2017
Highway : 11
Length of Construction : 30.20 km
Close To : Gravenhurst
Type of Contract : Paving and rehabilitation.
Value of Contract : $7,699,192.00
Description : Grading, drainage, granular base, hot mix paving, electrical, and structural rehabilitation.
Traffic Impact : Highway 11 from 1.7 kilometres north of Severn River to 0.3 kilometres south of Taylor Road for 30.2 kilometres. There is no impact on traffic. Work stoppage for the winter, will resume in the spring of 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017

Top of page Top of page


Contract #: 2014-5137
Start of Construction : May 01, 2015
Estimated End of Construction : November 30, 2017
Highway : 60
Length of Construction : 0.00 km
Close To :
Type of Contract : Grading, Drainage, Granular Base Hot Mix Paving, Structure Replacement, Structure Rehabilitation, and Electrical
Value of Contract : $24,686,070.00
Description : Resurfacing of Highway 60 from junction of Highway 127 easterly for 19.2 kilometres. Rehabilitation of the Amable Creek Culvert, 8 kilometres east of Highway 127. Replacement of 3 culverts situated at 11, 11.3 and 26.5 kilometres west of Highway 127. Rehabilitation of the Madawaska River Bridge located 3.1 kilometres west of Highway 127 in Whitney.
Traffic Impact : There is no impact on traffic. Lane closure will be in effect on Highway 60 within the limits of the project. Weekday sunrise to sunset single lane closures controlled by traffic control persons. Speed will be reduced to 50 kilometers per hour at Madawaska River bridge. Bridge widths of 4.80 meters westbound, 4.57 meters eastbound with a 1.50 meter sidewalk are in the finished condition. Staged construction at culvert 26.5 kilometres west of Highway 127, down to one 4.5 metre lane width controlled by temporary traffic signals, speed reduced to 60 kilometers per hour both directions. This configuration will be in place until the culvert replacement is completed in the summer of 2017. Culvert #43-234: will be down to a 8.65 total platform width in Stage 2, Traffic control barrels on both sides of the roadway. This configuration will be in place until the culvert replacement is completed in the summer of 2017. The culvert is located 11.3 kilometres west of Highway 127. Speed reduced to 60 kilometres per hour.Work shut down for the winter months, will resume in spring 2017.
Region of Ontario : Northeastern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: January 20, 2017 - January 27, 2017
Last Updated: January 20, 2017