Construction Reports: Northwestern

Contract #: 2014-6032
Start of Construction : May 06, 2015
Estimated End of Construction : October 16, 2015
Highway : 61
Length of Construction : 0.00 km
Close To : Thunder Bay
Type of Contract : Structure Replacement, Grading, Granular Base, Hot Mix Paving
Value of Contract : $4,958,823.00
Description : Pine River bridge replacement 9.9km north Canada U.S. Pigeon River border crossing (or 6.8 kilometres north of Highway 593 or 25.5 kilometres south Highway 608)
Traffic Impact : Highway 61, Pine River Bridge, 9.9 kilometres North of Pigeon River, USA/CANADA Border. Expect delays up to 5 minutes. One lane closed for stage 1 construction. Effective May 4th, 2015, lane restriction is 3.8 metres width. Temporary traffic lights in place. Regulatory speed limit is 70 kilometres per hour, reduced to 50 kilometres per hour in areas.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6030
Start of Construction : February 25, 2015
Estimated End of Construction : June 30, 2015
Highway : 17
Length of Construction : 0.50 km
Close To : Cavers
Type of Contract : Rock Hazard Removal
Value of Contract : $2,473,949.00
Description : Rock face work 9.3 kilometres west of Pays Plat River westerly 0.5 kilometres, length of signing 4 kilometres (Cavers Hill, class A rock hazard)
Traffic Impact : Highway 17, 9.3 kilometres west of Pays Plat River westerly 0.5 kilometres (Cavers Hill). There is no impact on traffic. There are no lane restrictions or closures.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6029
Start of Construction : March 04, 2015
Estimated End of Construction : October 30, 2015
Highway : 102
Length of Construction : 0.00 km
Close To : Conmee
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Rehabilitation
Value of Contract : $8,110,310.00
Description : Strawberry Creek bridges #1, #2, and #3 rehabilitations starting 5.5 kilometres east Highway 11/17 (or 25.9 kilometres west Highway 11/17 or 19.2 kilometres west Highway 589 or #1 25.9 kilometres west Highway 11/17, #2 26.6 kilometres west Highway 11/17, and #3 27.6 kilometres west Highway 11/17)
Traffic Impact : Strawberry Creek bridge number 1, 7.1 kilometres east of junction Highway 102 and 11/17, number 2, 6.2 kilometres east of junction Highway 102 and 11/17, and number 3, 5.4 kilometres east of junction Highway 102 and 11/17. Expect delays up to 10 minutes. Effective April 8, 2015 at Strawberry Creek #2, traffic will encounter signals regulating single lane closure controlled by temporary concrete barriers. Effective April 9, 2015 at Strawberry Creek #3, traffic will encounter signals regulating single lane closure controlled by temporary concrete barriers. Effective april 13, 2015 at Strawberry Creek #1, traffic will encourter signals regulating single lane closure controlled by temporary concrete barriers. The single lanes are restricted to a 3.72 metre width at Strawberry Creek #1, #2, #3. The regulatory speed is reduced to 70 kilometres per hour.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6028
Start of Construction : January 28, 2015
Estimated End of Construction : October 30, 2015
Highway : 72
Length of Construction : 0.00 km
Close To : Sioux Lookout
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Bridge Replacement
Value of Contract : $7,637,227.00
Description : Pelican River bridge site 41S-009 replacement Sioux Lookout or 6.5 kilometres north Highway 664 or 66.7 kilometres north Highway 17
Traffic Impact : 6.5 kilometres north Highway 664 or 66.7 kilometres north Highway 17 Expect delays up to 5 minutes. The northbound lane will be closed to traffic. Temporary concrete barriers in place. Lane width reduced to 3.7 metre lane width. Traffic lights operational until contract completion.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6027
Start of Construction : January 21, 2015
Estimated End of Construction : October 23, 2015
Highway : 17
Length of Construction : 0.00 km
Close To : Marathon
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Replacement
Value of Contract : $4,721,243.00
Description : Cedar Creek culvert replacement 1.8 kilometres west Highway 614
Traffic Impact : Cedar Creek Bridge 1.8 kilometres west of Highway 614. Expect delays up to 5 minutes. There are no lane restrictions or closures at this time.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6025
Start of Construction : January 28, 2015
Estimated End of Construction : September 23, 2015
Highway : 628
Length of Construction : 0.00 km
Close To : Red Rock
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Replacement
Value of Contract : $2,415,140.00
Description : Big Trout Creek culvert replacement 2.5 kilometres south of junction Highway 628 and Highway 11/17.
Traffic Impact : Big Trout Creek, 2.5 kilometres south of junction Highway 628 and Highway 11/17 Expect delays up to 5 minutes. Installation of temporary concrete barriers on April 8, 2015. Lane closure at Big Trout Creek restricted to 3.8 metre lane width. Traffic lights operational until contract completion. The regulatory speed is reduced to 60 kilometers per hour.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6024
Start of Construction : February 28, 2015
Estimated End of Construction : September 04, 2015
Highway : 11
Length of Construction : 0.00 km
Close To : Longlac
Type of Contract : Structural Rehabiliation
Value of Contract : $7,159,254.00
Description : Part 1) Pagwachuan River east culvert site replacement 64.9km west Hwy 631 or 67.1km east Hwy 625. Part 2) Pagwachaun River west culvert site 48E-085C replacement 68.1km west Hwy 631 or 63.8km east Hwy 625. Part 3) Pagwachuan River Tributary culvert replacement 73.5km west Hwy 631 or 3.8km west North Pagwachuan River or 58.5km east Hwy 625
Traffic Impact : Highway 11, Pagwachuan River Tributary, 24.0 kilometres west of Junction Highway 11 and Highway 625. There is no impact on traffic. Effective may 18, 2015, traffic will encounter signals which regulate a single lane closure. The single lane is restricted to 3.9 metres width.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6023
Start of Construction : December 03, 2014
Estimated End of Construction : September 18, 2015
Highway : 613
Length of Construction : 0.00 km
Close To :
Type of Contract : Structure Replacement
Value of Contract : $5,703,771.00
Description : Part 1, Hastie River bridge replacement 3.8 kilometres north Highway 11 Devlin. Part 2, Munro River bridge replacement 16.9 kilometres north Highway 11 Devlin.
Traffic Impact : Highway 613, Hastie River Bridge 3.8 kilometres north Highway 11 Devlin and Munro River bridge 16.9 kilometres north Highway 11 Devlin. Expect delays up to 5 minutes. Effective April 6, 2015, traffic will encounter signals regulating single lane closure controlled by temporary concrete barriers. The single lane is restricted to a 4.2 meter width at Hastie River Bridge and 3.7 meter width at Munro River Bridge. The regulatory speed will be reduced to 60 kilometres per hour.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6020
Start of Construction : October 11, 2014
Estimated End of Construction : June 24, 2015
Highway : 11
Length of Construction : 1.00 km
Close To : Nipigon
Type of Contract : Rock Hazard Removal
Value of Contract : $2,921,750.00
Description : Smith Bay Rock Removal (Rock Excavation) 8.8 kilometres north Highway 11/17 Nipigon northerly 0.5 kilometres.
Traffic Impact : Highway 11, 9.0 kilometres north junction Highways 11, 17 and 11/17. There is no impact on traffic. There are no lane restrictions or closures.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6017
Start of Construction : October 03, 2014
Estimated End of Construction : September 25, 2015
Highway : 527
Length of Construction : 0.00 km
Close To : Armstrong
Type of Contract : Grading, Granular Base, Hot Mix, Paving, Embankment Rehabilitation, Structure Replacement, Structure Rehabilitation
Value of Contract : $8,694,960.00
Description : Part 1) Kabitotikwia River bridge replacement 32.4 kilometres north Hwy 811 or 0.4km north Hurket Road or 145.8 kilometres north Hwy 11/17 Part 2) Gull River bridge rehabilitation near Gull Bay 56.3km north Hwy 811 or 24.3km north Hurket Road or 169.7km north Hwy 11/17 3) Kopka River bridge rehabilitation 83.7 km north Hwy 811 or 51.75 kilometres north Hurket Road or 197.1 kilometres north Hwy 11/17
Traffic Impact : Highway 527, Kabitotikwia River Bridge, 32.4 kilometres North of Highway 811. Gull River Bridge, 56.3 kilometres North of Highway 811. Kopka River Bridge, 83.7 kilometres North of Highway 811. Expect delays up to 5 minutes. Effective May 24, 2015, Kopka River Bridge, single lane width restriction 3.7 metres by temporary concrete barriers. Speed limit reduced to 60 kilometres per hour in the work area.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6012
Start of Construction : August 27, 2014
Estimated End of Construction : September 18, 2015
Highway : 11
Length of Construction : 0.00 km
Close To : Shabaqua
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structure Replacement
Value of Contract : $2,754,000.00
Description : Kabaigon River bridge replacement 12.3 kilometres west Highway 586 (Burstrom's) or 33.1 kilometres west Highway 17 (Shabaqua).
Traffic Impact : Highway 11, Kabaigon River Bridge 33.1 kilometres west of south junction Highway 11 and Highway 17. Expect delays up to 15 minutes. Traffic is controlled by traffic control persons. Lane width restriction of 3.7 metres.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6009
Start of Construction : September 17, 2014
Estimated End of Construction : October 09, 2015
Highway : 17
Length of Construction : 0.00 km
Close To : Rossport
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Replacement
Value of Contract : $8,028,078.00
Description : CPR overhead near Rossport site 48C-024 replacement 0.3 kilometres west Rossport east road or 1.0 kilometres east Rossport Road west connection or 69.1 kilometres east Highway 11
Traffic Impact : CPR Overhead Bridge at Rossport, 69.1 kilometres east of south junction Highway 11 and Highway 17. Expect delays up to 5 minutes. Effective April 2015, traffic will encounter signals regulating single lane closure controlled by temporary concrete barriers. The single lane is restricted to a 3.7 metre width. The regulatory speed will be reduced to 70 kilometres per hour
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6008
Start of Construction : July 16, 2014
Estimated End of Construction : June 30, 2015
Highway : 594
Length of Construction : 4.10 km
Close To : Dryden
Type of Contract : Grading, Drainage, Granular Base, and Hot Mix Paving
Value of Contract : $5,009,776.00
Description :
Traffic Impact : Highway 594, from 0.1 kilometres west of Highway 502, easterly for 4.4 kilometres to the Dryden west limit. Highway 601 from the east junction with Highway 17, northerly for 5.0 kilometres. Expect delays up to 5 minutes. Highway 594, Traffic restricted to a single lane by Traffic Control persons. Reduced speed limit to 60 kilometres per hour. Highway 601, there are no lane restrictions or closures.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6007
Start of Construction : August 20, 2014
Estimated End of Construction : October 05, 2015
Highway : 17
Length of Construction : 0.00 km
Close To : Schreiber
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structural Replacement
Value of Contract : $4,191,000.00
Description : C P R Overhead site 48E-016 rehabilitation 1.4 kilometres east Schreiber limits or 93.2 kilometres east Highway 11 at CPR Mileage 115.85.
Traffic Impact : C P R Overhead, 93.2 kilometres east of south junction Highway 11 and 17 at CPR Mileage 115.85 Expect delays up to 5 minutes. Single lane restriction (3.7metre width) controlled by signals. Reduced speed limits 70 kilometres per hour within the construction zone.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6004
Start of Construction : July 02, 2014
Estimated End of Construction : May 06, 2015
Highway : 11
Length of Construction : 16.34 km
Close To : Atikokan
Type of Contract : Grading, drainage, Granular Base, Hot Mix Paving and Partial Illumination
Value of Contract : $8,087,813.00
Description : Part 1) Highway 11, 2.0 kilometres west Highway 623 Sapawe westerly 16.7 kilometres to 0.2 kilometres west Highway 11 B Atikokan. Part 2) Highway 11 B, from Highway 11 northerly 3.4 kilometres including illumination replacements.
Traffic Impact : Highway 11, from 0.4 kilometres west of the intersection of Highway 11B (Atikokan) Easterly for 16.9 kilometres; Highway 11B from the intersection of Highway 11 Northerly for 3.4 kilometres to Atikokan There is no impact on traffic. There are no lane restrictions in place. There are no reduced speed limits in effect.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6003
Start of Construction : July 07, 2014
Estimated End of Construction : June 12, 2015
Highway : 61
Length of Construction : 20.60 km
Close To : Thunder Bay
Type of Contract : Grading, Drainage, Granular Base and Hot Mix Paving
Value of Contract : $10,472,096.00
Description : Part 1) Pigeon River Canada US Border northerly 20.6 kilometres Part 2) Foundation Slip Failure Treatment between Cloud River Road and Jarvis Bay Road Part 3) tbd customs and tourist information areas Part 4) advance crushing of Granular A in Highway 61 quarry 20.7 kilometres north US border
Traffic Impact : from US/Canada Border, northerly for 20.6 kilometres. There is no impact on traffic. There are no lane restrictions or closures. Alternate Route: North on Highway 593 to East on Highway 588 to South on Highway 11.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6002
Start of Construction : July 02, 2014
Estimated End of Construction : June 30, 2015
Highway : 11
Length of Construction : 23.10 km
Close To : Jellicoe
Type of Contract : Grading and Paving
Value of Contract : $6,670,702.00
Description : 10.1 kilometres west Jellicoe (or 0.7 kilometres east Auden Tertiary access road / old Highway 801) westerly 23.1 kilometres to 0.8 kilometres west Highway 580 near the Blackwater River Bridge in Beardmore grading and Warm Mix Paving
Traffic Impact : 10.1 kilometres west of Jellicoe, westerly 23.1 kilometres to 0.8 kilometres west of Highway 580 at the Blackwater River Bridge in Beardmore. There is no impact on traffic. There are no lane restrictions or closures.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6001
Start of Construction : June 04, 2014
Estimated End of Construction : June 30, 2015
Highway : 17
Length of Construction : 28.20 km
Close To : Kenora
Type of Contract : Curve realignment, milling, paving, and rock excavation.
Value of Contract : $7,001,722.00
Description : Part 1) Highway 17, 11.2 kilometres east Highway 71 easterly 28.2 kilometres. Part 2) Highway17, horizontal curve revision 1.9 kilometres east Highway 71 westerly 0.7 kilometres.
Traffic Impact : from 1.2 kilometres east of highway 71 easterly for 0.7 kilometres, from 11.2 kilometres east of highway 71 easterly for 28.8 kilometres, from 7.0 kilometres east of highway 71 easterly for 0.6 kilometres. There is no impact on traffic. There are no lane restrictions or closures.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2014-6000
Start of Construction : September 04, 2014
Estimated End of Construction : September 27, 2016
Highway : 17
Length of Construction : 0.00 km
Close To : Marathon
Type of Contract : Structure rehabilitation, and completion of detour
Value of Contract : $11,517,000.00
Description : Part 1) "RE AWARD" for the Pic River bridge site 48E-025 rehab 7.2km east Marathon or 0.3 km east Hwy 627 Part 2) one lane signalized temporary detour including structure now separated from this project and tendered under 6048-13-00, an HST exemption was required for this detour Part 3) advance purchase of modular for detour cancelled - originally tendered under 6017-11-00 Part 4) the removal of the 6048-13-00 detour will be under this project Part 5) old WP 6137-09-01 was unassociated but left in CID
Traffic Impact : Pic River Bridge 7.2 kilometres East of Marathon. Expect delays up to 10 minutes. Effective April 7, 2015, traffic will encounter signals regulating single lane closure controlled by temporary concrete barriers. The single lane is restricted to a 4.3 metre width. The regulatory speed will be reduced to 70 kilometres per hour.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2013-6013
Start of Construction : December 20, 2013
Estimated End of Construction : October 20, 2015
Highway : 17
Length of Construction : 0.00 km
Close To : Ignace
Type of Contract : Culvert Replacement
Value of Contract : $2,944,000.00
Description : Part 1) Highway 17 Raleigh Lake Culvert replacement 9.5 kilometres east Hwy 622. Part 2) Hwy 72 Abram Lake (alias Patara Creek) Culvert replacement 0.2 km south Highway 664.
Traffic Impact : Highway 17, Raleigh Creek Culvert 9.5 kilometres East of Highway 622. There is no impact on traffic. Temporary concrete barriers in place. Lane width restriction is 4.3 metres.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2013-6000
Start of Construction : June 28, 2013
Estimated End of Construction : July 28, 2017
Highway : 11
Length of Construction : 0.00 km
Close To : Nipigon
Type of Contract : Construction of a new four-lane cable stayed bridge over the Nipigon River and widening of the approaches to the bridge to four lanes.
Value of Contract : $118,227,470.00
Description :
Traffic Impact : Highway 11/17, from 1.7 kilometres east of the junction Highway 11/17 (Nipigon) westerly to First Street. Expect delays up to 10 minutes. Traffic is controlled by Traffic Control Persons. Temporary staging in place around construction for north and southbound traffic. There are 3.5 meter wide delineated through lanes and 1.0 meter shoulders in place for areas immediately adjacent to the existing Nipigon River Bridge. Effective width of approximately 5.0 metres available for wide loads.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015

Top of page Top of page


Contract #: 2012-6022
Start of Construction : May 21, 2013
Estimated End of Construction : June 30, 2015
Highway : 17
Length of Construction : 17.36 km
Close To : Nipigon
Type of Contract : Structural
Value of Contract : $18,468,706.00
Description : Part 1) resurfacing from Jackfish River 13.4 kilometres east Highway 11 Nipigon easterly 31.2 kilometres. Part 2) Jackfish River Bridge 13.4 kilometres east Highway 11 replacement. Part 3) Jackpine River Bridge, 24.6 kilometres east Highway 11 rehabilitation. Part 4) foundation stabilization berm 3.5 kilometres west Little Gravel River or 40.8 kilometres east Highwy 11 in Wiggins Township (Notes: advance crushing of Granular A and 12.5 stone under minor caps, Dublin Creek realignment removed from this project)
Traffic Impact : 13.4 kilometres east of Highway 11 and 17 junction at Jackfish River Bridge, and 24.6 kilometres from the junction of Highway 11 at the Jackpine River Bridge. Expect delays up to 5 minutes. Lane closure at Jackfish River Bridge restricted to 4.5 metre lane width. Speed limit is reduced to 50 kilometres per hour. Two lanes open to public traffic on Jackpine River Bridge. There is no lane restriction. Periodic flagging for cleanup and other minor work on construction site. Alternative route, Highway 11.
Region of Ontario : Northwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: May 22, 2015 - May 29, 2015
Last Updated: May 22, 2015