Construction Reports: Southwestern

Contract #: 2014-3010
Start of Construction : July 14, 2014
Estimated End of Construction : June 24, 2015
Highway : 10
Length of Construction : 16.00 km
Close To : Shelburne
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Electrical.
Value of Contract : $6,395,301.00
Description : Resurfacing from Dufferin Road 17 to Dundalk - 12.1 kilometres, Dundalk to Flesherton - 16.3 kilometres Flesherton to Grey Rd. 130 - 4.2 kilometres (Total combined length = 32.6 kilometres.
Traffic Impact : From the intersection of Highway 10 and Dufferin Road 17, to 0.6 kilometres North of Highway 10 and Southgate Road 24. Expect delays up to 5 minutes. Short Duration Single Lane closure for 0.5 kilometres within contract limits. Monday to Friday 7:00 a.m. to 7:00 p.m.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3009
Start of Construction : July 02, 2014
Estimated End of Construction : June 23, 2015
Highway : 9
Length of Construction : 8.00 km
Close To : Kincardine
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Electrical
Value of Contract : $8,180,702.00
Description : Highway 21 to Bruce Road 7/Side Road 20, Kincardine - Resurfacing
Traffic Impact : From the junction at highway 21, Kincardine, to 0.14 Kilometres West of junction at Bruce Road 7. Expect delays up to 5 minutes. Highway 9 from Kincardine to Bruce Road 7 is closed 24 hours 7 days a week. Short Duration Single lane restrictions throughout contract. Monday to Friday 7:00 a.m. to 7:00 p.m.. Highway 9 from Kincardine to Bruce Road 7 is closed. Detour: Highway 21 to South Line to Bruce Road 7.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3007
Start of Construction : July 21, 2014
Estimated End of Construction : September 30, 2014
Highway : 6
Length of Construction : 4.80 km
Close To : Guelph
Type of Contract : Grading, Drainage, Hot Mix Paving, Granular Base, Electrical,
Value of Contract : $4,921,137.00
Description : Hanlon Expressway (Highway 6) - Highway 401 to South of Clair Road. Resurfacing 4.8 kilometres.
Traffic Impact : From Highway 401 Northerly to 0.92 kilometres South of Laird Road Interchange. Expect delays up to 15 minutes. Daytime: Highway 6 Southbound/Northbound. Two lane closures will be in effect from 10:00-21:00 on Monday September 22, 2014 to Thursday September 25, 2014. A single lane width and shoulder will be maintained through the closures. Highway 401 North-East and North-West On and Off Ramp will be closed between 10:00-21:00 Saturday September 27, 2014. Highway 401 East-North and West-North On and Off Ramp will be closed between 10:00-21:00 Sunday September 28, 2014. Reduced speed limit of 60 kilometres per hour will be in effect through the construction zone. There are currently no detours in effect During Southbound closure traffic will run North/South using the two Northbound lanes. During Northbound closure traffic will run North/South using the two Southbound lanes Alternate route will be in place.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3006
Start of Construction : July 01, 2014
Estimated End of Construction : December 31, 2014
Highway : 3
Length of Construction : 1.00 km
Close To : Tillsonburg
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Concrete Paving, and Electrical – Construction of Roundabout and Isles
Value of Contract : $2,755,044.00
Description : Intersection Improvements - Roundabout at Highway 3 & Vienna Road.
Traffic Impact : 0.9 kilometres of Highway 3 at the intersection of Highway 3 and Vienna Road. Expect delays up to 15 minutes. Alternating Lane Closure on Highway 3 and alternating Full Closure of Vienna Road North and South, while providing special access to Emergency Services Vehicles via Vienna Road at all time. Special Notes: 1-Due to possible fluctuation(s) in the Contractor’s Operation(s), notification(s) that are communicated directly by the contractor after distribution of this report will supersede this report. 2-Due to the Designation of Construction Zone for this contract, the Regulatory Speed Reduction Signs have been placed in the Construction Zone. 3-By decommissioning the Traffic Signals, the intersection has turned into a 3-way with Stop Sign on Vienna Road only. 4-Stage 2 of operation is in progress and operations are continuing at the North side of the Highway 3. As the result: Vienna Road North is Closed to commuters, while maintaining special access for Emergency Services Vehicles Only. Vienna Road South is Open to the commuters and Highway 3 traffic is shifted southerly as a Two-Way Road. Detour 1: Highway 3 - John Pound Road - Broadway Street – Oxford Street – Simcoe Street – Highway 3 – Bell Mill Side Road – Rokeby Orchard Road – Norfolk County Road 30 – Vienna Road. Detour 2: Highway 3- Carson Line – County Road 19 (Vienna Road)
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3004
Start of Construction : August 03, 2014
Estimated End of Construction : October 30, 2015
Highway : 6
Length of Construction : 0.00 km
Close To : Wiarton
Type of Contract : Structural Culvert Rehabilitations &Structural Culvert Replacement (Hot Mix Paving, Electrical & Structures)
Value of Contract : $7,309,435.00
Description : Structural Culvert Rehabilitations &Structural Culvert Replacement (Hot Mix Paving, Electrical & Structures)
Traffic Impact : From Hepworth to Ferndale, Bruce County. 42 kilometres (Various locations) For the year of 2014. Expect delays up to 5 minutes. Alternating lane closures Northbound and Southbound along Highway 6 for culvert rehabilitation and replacement. Traffic will be in a single lane configuration controlled by Traffic Control Persons.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3002
Start of Construction : July 21, 2014
Estimated End of Construction : October 14, 2014
Highway : 6
Length of Construction : 8.20 km
Close To : Hagersville
Type of Contract : Grading, Drainage, granular base, Hot Mix Paving and Electrical
Value of Contract : $4,242,107.00
Description : Jarvis to Hagersville - Resurfacing 8.2 kilometres eastbound and westbound.
Traffic Impact : From north limit of Jarvis to south limit of Hagersville. Total length 8.0 kilometres. Expect delays up to 10 minutes. Northbound and Southbound lanes will be flagged for placing center line culverts, ditch clean out and concrete culvert rehab. Milling, paving at various locations within the contract limits and guide rail installations. Regulatory speed limit has been reduced to 60 Kilometres within the construction zone Detour: Highway 3 and side roads.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3001
Start of Construction : August 07, 2014
Estimated End of Construction : November 21, 2014
Highway : 40
Length of Construction : 20.45 km
Close To : Chatham
Type of Contract : Grading, Drainage, Hot Mix Paving and Electrical
Value of Contract : $4,941,940.00
Description : Chatham to Wallaceburg Highway Resurfacing 19.8 kilometers in length
Traffic Impact : From Pioneer Line northerly to 1.5 kilometers north of Heritage Line. 19.8 kilometers in length. Expect delays up to 15 minutes. Weekday Operations Partial depth asphalt removal. Regulatory 60 kilometers per hour speed reduction within Flagging operations if required.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2014-3000
Start of Construction : August 11, 2014
Estimated End of Construction : November 28, 2014
Highway : 7
Length of Construction : 6.30 km
Close To : Guelph
Type of Contract : Intersection widening and road resurfacing.
Value of Contract : $3,998,939.00
Description : Guelph to Rockwood - Resurfacing 6.3 kilometres, westbound and eastbound lanes, intersection improvements at Highway 7 and Wellington County Road 44.
Traffic Impact : at Wellington Road 44 at Highway 7 4th Line. There is no impact on traffic. Lane and shoulder closures either Eastbound or Westbound for Earth Excavation and Granular fill.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3021
Start of Construction : May 30, 2014
Estimated End of Construction : September 24, 2015
Highway : 403
Length of Construction : 1.60 km
Close To : Brantford
Type of Contract : Structural Rehabilitation
Value of Contract : $8,426,289.00
Description : Grand River Bridge Rehabilitation.
Traffic Impact : Grand River Bridge structure 0.8 Kilometres Eastbound and 0.8 Kilometres Westbound. Expect delays up to 5 minutes. Speed reduced to 80 kilometres per hour through site. Median lane closed.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3019
Start of Construction : May 26, 2014
Estimated End of Construction : October 17, 2014
Highway : 402
Length of Construction : 0.00 km
Close To : London
Type of Contract : Rehabilitations of Bridges on Highway 402
Value of Contract : $6,003,300.00
Description : Structure Rehabilitation- highway 402- Miller Road Underpass, Springer Road Underpass, Carriage Road. Underpass, Sharon Road Underpass, Woodhull Road. Underpass, Westdel Bourne Underpass, White Oak Road. Underpass.
Traffic Impact : Underpasses at White Oak Road, Woodhull Road, Springer Road Expect delays up to 10 minutes. Highway 402 at White Oak Road, Eastbound and Westbound lanes may be reduced to one lane in vicinity of White Oak Road. Highway 402 at Woodhull Road, Eastbound and Westbound lanes may be reduced to one lane in vicinity of Woodhull Road. West and Eastbound shoulder closures. Highway 402 at Springer Road, Eastbound and Westbound lanes may be reduced to one lane in vicinity of Springer Road. Flagging operation at White Oak Road at Highway 402. Flaggin operation at Woodhull Road at Highway 402. Flagging operation at Springer Road at Highway 402. Local Detour Provided
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3018
Start of Construction : May 05, 2014
Estimated End of Construction : November 29, 2014
Highway : 23
Length of Construction : 25.70 km
Close To : Mitchell
Type of Contract : Grading, Drainage, Hot Mix Paving and Electrical
Value of Contract : $10,911,129.00
Description : Resurfacing From Elginfield (Highway 7) northerly 36 km to the south limit of Mitchell (Frank Street). Repair or replacement of culverts, curb and gutter and steel beam guide rail- Length 36.0 kilomètres.
Traffic Impact : From Highway 7 Northerly 36.0 kilometres to Mitchell South Limit Expect delays up to 5 minutes. One lane closed at various locations for Culvert installations.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3016
Start of Construction : May 05, 2014
Estimated End of Construction : December 12, 2014
Highway : 21
Length of Construction : 20.50 km
Close To : Port Elgin
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural Rehabilitation
Value of Contract : $10,279,050.00
Description : Port Elgin to Southampton to Alvanley - 20.5 kilometres, Deck Rehabilitation of Sauble River Bridge.
Traffic Impact : Port Elgin North Limits to Southampton South Limits, Southampton North Limits to Alvanley 20.5 kilometres. Expect delays up to 5 minutes. September 7 to December 2014 Sauble River Bridge structural rehabilitation. One lane closure (Southbound) at all times twenty four hours a day, seven days a week. Lane reduced to 3.5 meters with .25 meter offset from traffic to Temporary Concrete Barrier. Speed reduced to 60 kilometers per hour. Traffic Signals in place on both ends of the structure. September 22 to 27 Craig Street to Alvanley Intermittent single lane closures throughout the construction zone. Traffic Control Persons and Traffic Control Barrels in place to direct traffic. September 22 to 27 Intersection Bruce Road 10 and Highway 21 Single lane closure for highway lighting installations.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3015
Start of Construction : May 05, 2014
Estimated End of Construction : December 15, 2014
Highway : 4
Length of Construction : 5.90 km
Close To : London
Type of Contract : Drainage, hot mix paving and electrical
Value of Contract : $3,265,890.00
Description : Talbotville to Highway 401 - Resurfacing.
Traffic Impact : from 0.3 kilometres north of Highway 3 northerly to 0.2 kilometres north of Highway 401. Total length 5.9 kilometres. Expect delays up to 10 minutes. A lane on each direction will remain open all time except single lane section south of Longhurst Line to the south limit of contract will be flagged for placing granular material and other remaining works on single lane section northbound and southbound lanes from August 4 -8, 2014. Alternate route: Highway 3 and side roads.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3014
Start of Construction : April 28, 2014
Estimated End of Construction : November 06, 2015
Highway : 401
Length of Construction : 0.00 km
Close To : Cambridge
Type of Contract : Grading, Drainage, Hot Mix Paving, Granular Base, Electrical, Structure Rehabilitation (1) and Structure Replacement (2)
Value of Contract : $18,946,042.00
Description : Replacement of Fountain Street Underpass and Speedsville Road Underpass, Rehabilitation of Ramp Underpass from Highway 8.
Traffic Impact : Between Regional Road 8 / King Street and Regional Road 24 / Hespeler Road. Expect delays up to 10 minutes. Highway 401 Eastbound and Westbound Lane Closures: Sunday, September 21 - 1 lane closure from 10 p.m. to midnight. Monday, September 22 to Thursday, September 25 - 2 to 1 lane closure from Midnight to 6 am, then single lane again from 8 pm to Midnight. Friday, September 26 - 2 to 1 lane closure Midnight to 5 am, to 6am and then single lane 9 pm to Midnight. Saturday, September 27 - 2 lane closure from Midnight to 9 a.m. Sunday, September 28 - 2 lane closure from 7 am to 8 am, then 1 lane closure 8 to 10 a.m., then single lane again from 10 p.m. to midnight. King Street / Shantz Hill Road and Highway 401 ON and OFF Ramp Closures: Sunday, September 21 to Friday, September 26 closed from 9 p.m. to 6 a.m. Friday, September 26 to Sunday, September 28 closed - Saturday to Sunday 9 p.m. to 8 a.m., then again at 9 p.m. to midnight Sunday. A Reduced speed limit of 80 kilometre/hour will be in effect through the single and two lane closures. ALTERNATE ROUTE: Detour routes remain in effect from May 5, 2014 to October 31, 2014. Detour Route to the East of Speedsville Road is Eagle Street to Hespeler Road to Maple Grove Road. Detour Route to the West of Speedsville Road is Eagle Street to Fountain Street to Maple Grove Road. ALTERNATE ROUTE: Detour routes remain in effect from June 9, 2014 to October 31, 2014. An alternate route for eastbound Highway 401 will take traffic south on King Street to the on ramp at Shantz Hill.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3013
Start of Construction : May 26, 2014
Estimated End of Construction : October 15, 2014
Highway : 401
Length of Construction : 0.40 km
Close To : London
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Structures
Value of Contract : $4,083,660.00
Description : Westminster Structure Replacement.
Traffic Impact : Underpass at Westminster Drive in London Ontario, 0.4 kilometres. Expect delays up to 5 minutes. Highway 401 Eastbound/Westbound speed reduced to 80 kilometre per hour. Westminster Drive Single Lane Closure (as needed). Highway 401 Westbound/Eastbound Single Lane Closure (as needed).
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3008
Start of Construction : April 01, 2014
Estimated End of Construction : December 23, 2014
Highway : 6
Length of Construction : 11.40 km
Close To : Chatsworth
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving and Electrical.
Value of Contract : $7,061,365.00
Description : Resurfacing from Chatsworth to Owen Sound - 11 kilometres, Addition of Left Turn Lanes and Partial Illumination at the intersection of Grey Road 16, Various upgrades to existing Truck Inspection Site South of Owen Sound.
Traffic Impact : Highway 6 & 10 From North Limit of Chatsworth to South Limit of Owen Sound. Length of Contract 11.4 kilometres. Expect delays up to 20 minutes. Single lane closures for operations ongoing from Chatsworth to Owen Sound controlled by Traffic Control Persons thoughout the day. As per detour signage.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2013-3003
Start of Construction : July 02, 2013
Estimated End of Construction : October 31, 2014
Highway : 89
Length of Construction : 0.00 km
Close To : Shelburne
Type of Contract : Grading, drainage, granular base, hot mix paving, electrical and structural replacement / rehabilitation
Value of Contract : $6,213,810.00
Description : Replacement of South Saugeen River Bridge, South Saugeen River Bridge Rehabilitation, Mud Creek Bridge Rehabilation and Grand River (Keldon) Bridge Replacement.
Traffic Impact : West of Mount Forest (Conn) to east of Shelburne (Keldon). Expect delays up to 25 minutes. Short duration temporary single shoulder/lane closures. Regulatory Speed reduction to 60 kilometres per hour. Reduced to one lane with temporary traffic signals at Mud Creek Structure. Reduced to one lane with temporary traffic signals at South Saugeen River East bridge. Wellington Road 16 at Highway 89 South Saugeen East Bridge closed to Traffic at Highway 89. Reduce to one lane with temporary traffic signals at Culvert 35-512C. There is a lane restriction of 4.35 metre width. Detour Route # 1 (travelling Wellington Road 16 South) Highway 89 west to Wellington Road 14 south to Line 8 east to Wellington 16 South. Approximately 20 kilometres. Detour Route # 2 (travelling Wellington Road 16 North) Line 8 east to Wellington Road 14 north to Highway 89. Approximately 20 kilometres.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3034
Start of Construction : May 01, 2014
Estimated End of Construction : November 29, 2014
Highway : 403
Length of Construction : 0.00 km
Close To : Brantford
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural Rehabilitation
Value of Contract : $11,769,200.00
Description : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural Rehabilitation.
Traffic Impact : King George Road, Ewing Drive and West Street Underpasses. There is no impact on traffic. Ramp to Eastbound Highway 403 at King George Road closed for Southbound traffic on King George Road.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3032
Start of Construction : April 11, 2013
Estimated End of Construction : October 24, 2014
Highway : 3
Length of Construction : 0.00 km
Close To : St. Thomas
Type of Contract : Structural Rehabilitations
Value of Contract : $6,522,825.00
Description : Rehabilitations of Kettle Creek Branch Bridge, First Avenue Underpass, Balaclava Street Underpass, Burwell Road Underpass, St. Thomas Bypass, Highway 4-Replacement of Dodds Creek Culvert.
Traffic Impact : (Kettle Creek Overpass, Balaclava Street Underpass, First Avenue Interchange and Burwell Street Underpass 3.1 kilometres Highway 4 (Dodds Creek Culvert at North Side of Talbotville) 1.0 kilometre. Expect delays up to 5 minutes. March 24-28, 2014 Ongoing work will include occasional single lane closures with flagging. Minimal delays during flagging operations. No reduced speed limits. No detour routes on Highway 3; Detour route in place for Northbound Traffic on Balaclava Street in Saint Thomas
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3022
Start of Construction : April 28, 2014
Estimated End of Construction : October 03, 2015
Highway : 401
Length of Construction : 4.00 km
Close To : London
Type of Contract : New Interchange
Value of Contract : $18,283,415.00
Description : Highway 401-New Interchange at Wonderland Road, London-Design Build.
Traffic Impact : From 0.5 kilometres West of the Glanworth Drive underpass easterly to 1.0 East of the Scotland Drive underpass. Expect delays up to 5 minutes. Highway 401 Eastbound and Westbound lanes - ongoing single lane closures and speed reduction.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3015
Start of Construction : October 01, 2012
Estimated End of Construction : October 31, 2014
Highway : 401
Length of Construction : 0.00 km
Close To : Windsor
Type of Contract : Grading, Granular Hot Mix Paving, Concrete Paving, Drainage, Electrical, ATMS, Structural and Building Sciences.
Value of Contract : $20,358,000.00
Description : EXPANSION AND RECONFIGURATION OF THE CANADIAN PLAZA OF THE WINDSOR-DETROIT TUNNEL INCLUDING ROADWAY IMPROVEMENTS.
Traffic Impact : Windsor-Detroit Tunnel Plaza Improvements, Windsor Ontario. Expect delays up to 15 minutes. Various lane closures, lane shifts and intersection closures on Wyandotte, Goyeau and Park Streets will occur. Goyeau Street, between Park and Wyandotte Streets is now permanently closed as of February 11, 2013. Access to the Tunnel to USA is only from Wyandotte Street. There is no through street from Wyandotte to Park. Temporary traffic control signage and detour signs will be erected for various stages of construction to direct traffic in and around the construction site. The Windsor-Detroit Tunnel will remain open and accessible at all times during construction.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3011
Start of Construction : October 22, 2012
Estimated End of Construction : November 30, 2014
Highway : 85
Length of Construction : 10.80 km
Close To : Waterloo
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural
Value of Contract : $32,305,105.00
Description : Grading, Drainage, Granular Base, Hot Mix Paving, Electrical and Structural.
Traffic Impact : Highway 7 and 85 from Krug Street to 0.4 kilometres North of Regional Road 15 10.8 Kilometres Expect delays up to 10 minutes. Operations to include Structure work at Lancaster Street, University Avenue and Regional Road 15 (underneath the structures and on Lancaster, University and Regional Road 15) for structure rehabilitation. Lane restrictions are in place on Lancaster Street, University Avenue and Regional Road 15 in vicinity of structures. Daytime shoulder / single lane closures on Highway 85 for culvert clean out, pipe lining work, granular shouldering, sign installation, and electrical removals. Daytime single lane closures are possible on Northfield Drive for work on expansion joints. Nighttime single lane and/or ramp closures on Highway 85 in the vicinity of Lancaster Street, Bridgeport Road, University Avenue, King Street, Northfield Drive, Lexington Avenue and Regional Road 15 for milling and paving operations, shouldering, concrete sealer application, guide rail and structure rehabilitation. All work is dependent on weather conditions. No Alternate Detour Route Required. University Avenue South-West Ramp remains closed and is to be closed until approximately October 17th, 2014.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3007
Start of Construction : July 25, 2012
Estimated End of Construction : October 05, 2015
Highway : 3
Length of Construction : 0.00 km
Close To : Dunnville
Type of Contract : Structural Replacement
Value of Contract : $27,953,735.00
Description : Replacement/Rehabilitation of Grand River Bridge Cayuga), Culvert Replacement in Cansfield, near Cayuga (CMGC Process Delivery Model).
Traffic Impact : Cayuga/Grand River – Structure 500 metres West of Grand River Bridge to 500 metres East of Grand River Bridge. Expect delays up to 5 minutes. Narrow Lanes – 3.25 metres at East and West Approaches. Recommended Speed of 30 kilometres per hour. Traffic shifted onto detour bridge. Contractor has traffic management in-place.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2012-3000
Start of Construction : May 22, 2012
Estimated End of Construction : August 29, 2014
Highway : 401
Length of Construction : 3.00 km
Close To : Guelph
Type of Contract : Structural Rehabilitation
Value of Contract : $4,458,709.00
Description : Structural rehabilitation.
Traffic Impact : Wellington Road 32 Underpass About 3 kilometres Highway 401 Wellington Road 35 Underpass About 3 kilometres Highway 401 Highway 6 North Underpass About 3 kilometres Expect delays up to 5 minutes. Highway 401 Wellington Road 32 Underpass Nightly Temporary Single and Double lane closures Eastbound and Westbound at the underpass, with a reduction of speed to 80 kilometres per hour. Highway 401 Wellington Road 35 Underpass Nightly Temporary Single and Double lane closures Eastbound and Westbound at the underpass, with a reduction of speed to 80 kilometres per hours. Highway 401 Highway 6 North Underpass Nightly Closures of North-East Ramp and West-North Ramp. North-West Ramp Deceleration lane closed. Highway 6 Southbound right lane reduction to become North-West Ramp exit. On Highway 401 Nightly Temporary Single and Double lane closures Eastbound and Westbound at the underpass, with a reduction of speed to 80 kilometres per hour. Detour: During North-East ramp nightly closures use Wellington Road 34 to reach Highway 6 South to go Eastbound on Highway 401.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014

Top of page Top of page


Contract #: 2011-3003
Start of Construction : October 01, 2011
Estimated End of Construction : October 31, 2015
Highway : 7
Length of Construction : 5.50 km
Close To : Kitchener
Type of Contract : Grading, Drainage, Granular Base, Hot Mix Paving, Structural, High Mast Illumination, Noise Barriers and ATMS
Value of Contract : $96,115,878.00
Description : Reconstruction from Fischer Hallman Road to Courtland Avenue, Kitchener 5.5 kilometres - Includes 12 Bridge Rehabilitation.
Traffic Impact : Highway 7/8: From 1.9 kilometres West of Fischer-Hallman Road Easterly to 0.8 kilometres East of Courtland Avenue. There is no impact on traffic. Courtland Avenue Westbound On Ramp: Closed for approximately 7 months. Homer Watson Boulevard - Southbound and Northbound: Reduced to a single lane in each direction at the interchange. Courtland Westbound Off Ramp: Closed Sunday and Monday night. 9 p.m. to 6 a.m.
Region of Ontario : Southwestern
Contact Name : Road Info
Contact Number : 1-800-268-4686 / 416 235-4686 TTY:905 704/2426/1-866-471-8929
Valid for the week of: September 19, 2014 - September 26, 2014
Last Updated: September 19, 2014