Current Events

Last Updated: October 01, 2016 18:29:24

Scheduled Events

Today's Roadwork
Planned Roadwork
HWY 11 Northbound [ LINE 6 - LINE 7/SIMCOE ROAD 27 ] - Recurring-Construction
Event Id: 63749
Highway: HWY 11
Direction: Northbound
Stream:
From/At: LINE 6
To: LINE 7/SIMCOE ROAD 27
Lanes Affected: 1 Alternating Lane(s)
Comment : Alternating 1 lane closure.
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 19:00
Event End: October 04, 2016 07:00
Last Change: Entered 2016-09-27 21:32
Last Updated: September 27, 2016 21:32

Top of page Top of page


HWY 11 Northbound Off-ramp [ - SEVERN RIVER BRIDGE/WEST BRANCH Northbound ] - Recurring-Maintenance
Event Id: 63838
Highway: HWY 11
Direction: Northbound
Stream: Off-ramp
From/At:
To: SEVERN RIVER BRIDGE/WEST BRANCH Northbound
Lanes Affected: ALL LANES CLOSED
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 02, 2016 20:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 14:52
Last Updated: September 28, 2016 14:52

Top of page Top of page


HWY 11 Southbound [ LINE 7/SIMCOE ROAD 27 - LINE 6 ] - Recurring-Construction
Event Id: 63750
Highway: HWY 11
Direction: Southbound
Stream:
From/At: LINE 7/SIMCOE ROAD 27
To: LINE 6
Lanes Affected: 1 Alternating Lane(s)
Comment : Alternating 1 lane closure.
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 19:00
Event End: October 04, 2016 07:00
Last Change: Entered 2016-09-27 21:34
Last Updated: September 27, 2016 21:34

Top of page Top of page


HWY 11 Southbound On-ramp [ SEVERN RIVER BRIDGE/WEST BRANCH Southbound - ] - Recurring-Maintenance
Event Id: 63839
Highway: HWY 11
Direction: Southbound
Stream: On-ramp
From/At: SEVERN RIVER BRIDGE/WEST BRANCH Southbound
To:
Lanes Affected: ALL LANES CLOSED
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 02, 2016 20:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 14:54
Last Updated: September 28, 2016 14:54

Top of page Top of page


HWY 26 Eastbound [ RAINBOW VALLEY ROAD - RICHARDSON ROAD ] - Recurring-Construction
Event Id: 63721
Highway: HWY 26
Direction: Eastbound
Stream:
From/At: RAINBOW VALLEY ROAD
To: RICHARDSON ROAD
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 07:00
Event End: October 06, 2016 15:00
Last Change: Entered 2016-09-27 14:12
Last Updated: September 27, 2016 14:12

Top of page Top of page


HWY 26 Eastbound [ SPENCE AVE/SIMCOE ROAD 27 - CARSON ROAD ] - Recurring-Construction
Event Id: 63991
Highway: HWY 26
Direction: Eastbound
Stream:
From/At: SPENCE AVE/SIMCOE ROAD 27
To: CARSON ROAD
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 20:00
Event End: October 06, 2016 05:00
Last Change: Entered 2016-09-30 09:21
Last Updated: September 30, 2016 09:21

Top of page Top of page


HWY 26 Westbound [ CARSON ROAD - SPENCE AVE/SIMCOE ROAD 27 ] - Recurring-Maintenance
Event Id: 63993
Highway: HWY 26
Direction: Westbound
Stream:
From/At: CARSON ROAD
To: SPENCE AVE/SIMCOE ROAD 27
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 03, 2016 20:00
Event End: October 06, 2016 05:00
Last Change: Entered 2016-09-30 09:26
Last Updated: September 30, 2016 09:26

Top of page Top of page


HWY 400 Northbound [ 5TH LINE - INNISFIL BEACH ROAD - SIMCOE ROAD 21 ] - Recurring-Construction
Event Id: 63748
Highway: HWY 400
Direction: Northbound
Stream:
From/At: 5TH LINE
To: INNISFIL BEACH ROAD - SIMCOE ROAD 21
Lanes Affected: 2 Alternating Lane(s)
Comment : Monday though Wednesday, one lane closed at 20:00, two lanes closed at 23:00, one lane opens at 06:00, all lanes open at 11.00. On thursday, one lane closed at 20:00, two lanes close at 23:00. One lane opens at 6:00, all lanes open at 8:00.
Traffic Impact : On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: September 30, 2016 23:59
Event End: October 02, 2016 09:00
Last Change: Entered 2016-09-27 17:57
Last Updated: September 27, 2016 17:57

Top of page Top of page


HWY 400 Northbound [ 5TH LINE - INNISFIL BEACH ROAD - SIMCOE ROAD 21 ] - Recurring-Construction
Event Id: 63843
Highway: HWY 400
Direction: Northbound
Stream:
From/At: 5TH LINE
To: INNISFIL BEACH ROAD - SIMCOE ROAD 21
Lanes Affected: 2 Alternating Lane(s)
Comment : Monday though Wednesday, one lane closed at 20:00, two lanes closed at 23:00, one lane opens at 06:00, all lanes open at 11.00. On thursday, one lane closed at 20:00, two lanes close at 23:00. One lane opens at 6:00, all lanes open at 8:00.
Traffic Impact : On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 20:00
Event End: October 07, 2016 11:00
Last Change: Entered 2016-09-28 15:04
Last Updated: September 28, 2016 15:04

Top of page Top of page


HWY 400 Northbound [ 5TH LINE - INNISFIL BEACH ROAD - SIMCOE ROAD 21 ] - Recurring-Construction
Event Id: 63840
Highway: HWY 400
Direction: Northbound
Stream:
From/At: 5TH LINE
To: INNISFIL BEACH ROAD - SIMCOE ROAD 21
Lanes Affected: 2 Alternating Lane(s)
Comment : On Sunday, one lane closed at 19:00, two lanes closed at 23:00, one lane opens at 06:00, all lanes open at 11.00.
Traffic Impact : On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: October 02, 2016 19:00
Event End: October 03, 2016 11:00
Last Change: Entered 2016-09-28 14:55
Last Updated: September 28, 2016 14:55

Top of page Top of page


HWY 400 Northbound [ DUCKWORTH STREET - DUCKWORTH STREET ] - Recurring-Maintenance
Event Id: 63810
Highway: HWY 400
Direction: Northbound
Stream:
From/At: DUCKWORTH STREET
To: DUCKWORTH STREET
Lanes Affected: 2 Alternating Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 03, 2016 22:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 12:53
Last Updated: September 28, 2016 12:53

Top of page Top of page


HWY 400 Northbound [ DUCKWORTH STREET - HWY 11 JCT ] - Construction
Event Id: 63909
Highway: HWY 400
Direction: Northbound
Stream:
From/At: DUCKWORTH STREET
To: HWY 11 JCT
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact : On-ramp from HWY 11 JCT NB
Type - Reason Planned - Construction
Event Start: October 03, 2016 06:00
Event End: October 03, 2016 18:00
Last Change: Entered 2016-09-27 16:47
Last Updated: September 27, 2016 16:47

Top of page Top of page


HWY 400 Northbound [ DUCKWORTH STREET - HWY 11 JCT ] - Recurring-Construction
Event Id: 63927
Highway: HWY 400
Direction: Northbound
Stream:
From/At: DUCKWORTH STREET
To: HWY 11 JCT
Lanes Affected: 2 Right Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 06, 2016 18:00
Event End: October 07, 2016 07:00
Last Change: Entered 2016-09-29 16:37
Last Updated: September 29, 2016 16:37

Top of page Top of page


HWY 400 Northbound [ ESSA ROAD / SIMCOE ROAD 27 - DUNLOP STREET / SIMCOE ROAD 90 ] - Recurring-Construction
Event Id: 63428
Highway: HWY 400
Direction: Northbound
Stream:
From/At: ESSA ROAD / SIMCOE ROAD 27
To: DUNLOP STREET / SIMCOE ROAD 90
Lanes Affected: 2 Alternating Lane(s)
Comment : On Monday expanding to two lanes closed at 22:00. on Tuesday to Thursday, one lane closure at 20:00, expanding to a 2 lane closure at 21:00. All lanes open at 06:00. On Friday, two lane closure at midnight. One lane opens at 06:00, all lanes open at 08:00. On Saturday, one lane closure at 19:00, expanding to a two lane closure at 23:00. One lane opens at 07:00, all lanes open at 09:00. On Sunday, one lane closure at 20:00, expanding to a two lane closure at 23:00. All lanes open at 06:00.
Traffic Impact : On-ramp from ESSA ROAD / SIMCOE ROAD 27 EB, On-ramp from ESSA ROAD / SIMCOE ROAD 27 WB, Off-ramp to DUNLOP STREET / SIMCOE ROAD 90 EB
Type - Reason Planned - Recurring-Construction
Event Start: September 25, 2016 23:00
Event End: October 01, 2016 23:59
Last Change: Entered 2016-09-21 11:19
Last Updated: September 21, 2016 11:19

Top of page Top of page


HWY 400 Northbound [ ESSA ROAD / SIMCOE ROAD 27 - DUNLOP STREET / SIMCOE ROAD 90 ] - Recurring-Construction
Event Id: 63773
Highway: HWY 400
Direction: Northbound
Stream:
From/At: ESSA ROAD / SIMCOE ROAD 27
To: DUNLOP STREET / SIMCOE ROAD 90
Lanes Affected: 2 Alternating Lane(s)
Comment : Sunday, one lanes closed at 20:00, two lanes closed at 23:00. Monday to Thursday, one lane closed 20:00, two lanes closed at 22:00. All lanes opened at 6:00 for all days.
Traffic Impact : On-ramp from ESSA ROAD / SIMCOE ROAD 27 EB, On-ramp from ESSA ROAD / SIMCOE ROAD 27 WB, Off-ramp to DUNLOP STREET / SIMCOE ROAD 90 EB
Type - Reason Planned - Recurring-Construction
Event Start: October 02, 2016 20:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 09:44
Last Updated: September 28, 2016 09:44

Top of page Top of page


HWY 400 Northbound [ WILLOW CREEK BRIDGE - HWY 11 JCT ] - Recurring-Construction
Event Id: 63569
Highway: HWY 400
Direction: Northbound
Stream:
From/At: WILLOW CREEK BRIDGE
To: HWY 11 JCT
Lanes Affected: 1 Right Lane(s)
Comment : On Friday, one lane closure from 23:00 to 07:00. On Saturday, one lane closure from 17:00 to 09:00. On Sunday, one lane closure from 09:00 to 18:00.
Traffic Impact : On-ramp from HWY 11 JCT NB
Type - Reason Planned - Recurring-Construction
Event Start: September 30, 2016 00:00
Event End: October 02, 2016 17:30
Last Change: Entered 2016-09-23 07:51
Last Updated: September 23, 2016 07:51

Top of page Top of page


HWY 400 Northbound [ WILLOW CREEK BRIDGE - HWY 11 JCT ] - Recurring-Construction
Event Id: 63744
Highway: HWY 400
Direction: Northbound
Stream:
From/At: WILLOW CREEK BRIDGE
To: HWY 11 JCT
Lanes Affected: 1 Right Lane(s)
Comment : Mainline closures: On Friday, single lane closure from 23:59 to 07:00. On Saturday, single lane closure from 17:00 to Sunday at 18:00. Single lane closure on Hwy 11 between Simcoe Rd 93 and Hwy 400 NB ramp jct on Friday from 23:59 to 10:00, Saturday from 19:00 to 08:00 and Sunday from 23:00 to 07:00.
Traffic Impact : On-ramp from HWY 11 JCT NB
Type - Reason Planned - Recurring-Construction
Event Start: October 07, 2016 23:00
Event End: October 09, 2016 18:00
Last Change: Entered 2016-09-27 17:03
Last Updated: September 27, 2016 17:03

Top of page Top of page


HWY 400 Northbound Off-ramp [ - PORT SEVERN ROAD Northbound ] - Recurring-Maintenance
Event Id: 63833
Highway: HWY 400
Direction: Northbound
Stream: Off-ramp
From/At:
To: PORT SEVERN ROAD Northbound
Lanes Affected: ALL LANES CLOSED
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 02, 2016 22:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 14:45
Last Updated: September 28, 2016 14:45

Top of page Top of page


HWY 400 Southbound [ CANAL ROAD. - AURORA ROAD. ] - Recurring-Construction
Event Id: 63654
Highway: HWY 400
Direction: Southbound
Stream:
From/At: CANAL ROAD.
To: AURORA ROAD.
Lanes Affected: 2 Alternating Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 19:00
Event End: October 07, 2016 05:00
Last Change: Entered 2016-09-26 12:02
Last Updated: September 26, 2016 12:02

Top of page Top of page


HWY 400 Southbound [ CANAL ROAD. - AURORA ROAD. ] - Recurring-Construction
Event Id: 63520
Highway: HWY 400
Direction: Southbound
Stream:
From/At: CANAL ROAD.
To: AURORA ROAD.
Lanes Affected: 2 Alternating Lane(s)
Comment : Mainline: Monday to Thursday one lane closed at 19:00, two lanes closed at 22:00. All lanes open at 05:00. On Friday, one lane closes at 22:00, two lanes at 23:59, one lane reopens at 6:00 and all lanes open at 8:00. On Saturday, one lane closes at 23:00, two lanes close at 23:59, one lane opens at 8:00 and all lanes open at 9:00. On Sunday, one lane closes at 23:00, two lanes at 23:59 and all lanes open at 5:00. On/Off-Ramp closure times: Monday 23:59-5:00, Tuesday to Thursday 23:00-5:00. Friday & Saturday 23:00-8:00, Sunday 23:00-5:00.
Traffic Impact : On-ramp from HWY 9 EB, Off-ramp to HWY 9 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: September 26, 2016 19:00
Event End: October 03, 2016 09:00
Last Change: Entered 2016-09-22 11:03
Last Updated: September 22, 2016 11:03

Top of page Top of page


HWY 400 Southbound [ DUNLOP STREET / SIMCOE ROAD 90 - ESSA ROAD / SIMCOE ROAD 27 ] - Recurring-Construction
Event Id: 63785
Highway: HWY 400
Direction: Southbound
Stream:
From/At: DUNLOP STREET / SIMCOE ROAD 90
To: ESSA ROAD / SIMCOE ROAD 27
Lanes Affected: 2 Left Lane(s)
Comment : Alternate two lane closure. On Monday to Thursday, one lane closes at 22:00, opens at 5:00 expanding to lane 2 closes at 22:00 and opens at 5:00. On Friday and Saturday One lane closes at 22:00 and opens at 07:00 & 6:00 expanding at lane 2 closes at 22:00 and opens at 7:00 & 5:00.
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: October 02, 2016 22:00
Event End: October 08, 2016 06:00
Last Change: Entered 2016-09-28 09:50
Last Updated: September 28, 2016 09:50

Top of page Top of page


HWY 400 Southbound [ DUNLOP STREET / SIMCOE ROAD 90 - ESSA ROAD / SIMCOE ROAD 27 ] - Recurring-Construction
Event Id: 63427
Highway: HWY 400
Direction: Southbound
Stream:
From/At: DUNLOP STREET / SIMCOE ROAD 90
To: ESSA ROAD / SIMCOE ROAD 27
Lanes Affected: 2 Alternating Lane(s)
Comment : Alternate two lane closure. On Monday to Thursday, one lane closes at 22:00, opens at 5:00 expanding to lane 2 closes at 22:00 and opens at 5:00. On Friday and Saturday One lane closes at 22:00 and opens at 07:00 & 6:00 expanding at lane 2 closes at 22:00 and opens at 7:00 & 5:00.
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: September 26, 2016 21:00
Event End: October 02, 2016 05:00
Last Change: Entered 2016-09-21 11:00
Last Updated: September 21, 2016 11:00

Top of page Top of page


HWY 400 Southbound [ HWY 11 JCT - DUCKWORTH STREET ] - Recurring-Construction
Event Id: 63722
Highway: HWY 400
Direction: Southbound
Stream:
From/At: HWY 11 JCT
To: DUCKWORTH STREET
Lanes Affected: 1 Alternating Lane(s)
Comment :
Traffic Impact : Off-ramp to HWY 11 JCT SB
Type - Reason Planned - Recurring-Construction
Event Start: September 30, 2016 20:00
Event End: October 02, 2016 09:00
Last Change: Entered 2016-09-23 09:03
Last Updated: September 23, 2016 09:03

Top of page Top of page


HWY 400 Southbound [ HWY 11 JCT - DUCKWORTH STREET ] - Recurring-Construction
Event Id: 63745
Highway: HWY 400
Direction: Southbound
Stream:
From/At: HWY 11 JCT
To: DUCKWORTH STREET
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact : Off-ramp to HWY 11 JCT SB
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 18:00
Event End: October 07, 2016 15:00
Last Change: Entered 2016-09-27 17:09
Last Updated: September 27, 2016 17:09

Top of page Top of page


HWY 400 Southbound [ HWY 11 JCT - DUCKWORTH STREET ] - Recurring-Construction
Event Id: 63746
Highway: HWY 400
Direction: Southbound
Stream:
From/At: HWY 11 JCT
To: DUCKWORTH STREET
Lanes Affected: 1 Alternating Lane(s)
Comment :
Traffic Impact : Off-ramp to HWY 11 JCT SB
Type - Reason Planned - Recurring-Construction
Event Start: October 07, 2016 20:00
Event End: October 09, 2016 09:00
Last Change: Entered 2016-09-27 17:14
Last Updated: September 27, 2016 17:14

Top of page Top of page


HWY 400 Southbound [ HWY 11 JCT - WILLOW CREEK BRIDGE ] - Construction
Event Id: 63913
Highway: HWY 400
Direction: Southbound
Stream:
From/At: HWY 11 JCT
To: WILLOW CREEK BRIDGE
Lanes Affected: 1 Left Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Construction
Event Start: October 05, 2016 18:00
Event End: October 06, 2016 15:00
Last Change: Entered 2016-09-29 14:50
Last Updated: September 29, 2016 14:50

Top of page Top of page


HWY 400 Southbound [ INNISFIL BEACH ROAD - SIMCOE ROAD 21 - 5TH LINE ] - Recurring-Construction
Event Id: 63747
Highway: HWY 400
Direction: Southbound
Stream:
From/At: INNISFIL BEACH ROAD - SIMCOE ROAD 21
To: 5TH LINE
Lanes Affected: 2 Alternating Lane(s)
Comment : On Friday, one lane closes at 19:00, two lanes close at 23:00, one of the closed lanes open at 07:00 and all lanes open at 09:00. On Saturday, one lane closes at 21:00, two lanes close at midnight. One of the closed lanes open at 07:00 and all lanes open at 10:00.
Traffic Impact : On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: September 30, 2016 19:00
Event End: October 02, 2016 10:00
Last Change: Entered 2016-09-27 17:49
Last Updated: September 27, 2016 17:49

Top of page Top of page


HWY 400 Southbound [ INNISFIL BEACH ROAD - SIMCOE ROAD 21 - 5TH LINE ] - Recurring-Construction
Event Id: 63834
Highway: HWY 400
Direction: Southbound
Stream:
From/At: INNISFIL BEACH ROAD - SIMCOE ROAD 21
To: 5TH LINE
Lanes Affected: 2 Alternating Lane(s)
Comment : One lane closes at 23:00, two lanes close at 23:59, all lanes open at 05:00. All Ramps closed from 23:00 to 05:00.
Traffic Impact : On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: October 02, 2016 23:00
Event End: October 03, 2016 05:00
Last Change: Entered 2016-09-28 14:52
Last Updated: September 28, 2016 14:52

Top of page Top of page


HWY 400 Southbound [ INNISFIL BEACH ROAD - SIMCOE ROAD 21 - 5TH LINE ] - Recurring-Construction
Event Id: 63842
Highway: HWY 400
Direction: Southbound
Stream:
From/At: INNISFIL BEACH ROAD - SIMCOE ROAD 21
To: 5TH LINE
Lanes Affected: 2 Alternating Lane(s)
Comment : One lane closes at 11:00, two lanes close at 22:00, all lanes open at 05:00. All Ramps closed from 23:00 to 05:00.
Traffic Impact : On-ramp from INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB, On-ramp from HWY 89/SIMCOE ROAD 89 EB/WB, On-ramp from SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to SERVICE CENTRE - COOKSTOWN ONROUTE SB EB/WB, Off-ramp to HWY 89/SIMCOE ROAD 89 EB/WB, Off-ramp to INNISFIL BEACH ROAD - SIMCOE ROAD 21 EB/WB
Type - Reason Planned - Recurring-Construction
Event Start: October 03, 2016 11:00
Event End: October 07, 2016 05:00
Last Change: Entered 2016-09-28 15:00
Last Updated: September 28, 2016 15:00

Top of page Top of page


HWY 400 Southbound On-ramp [ PORT SEVERN ROAD Southbound - ] - Recurring-Maintenance
Event Id: 63835
Highway: HWY 400
Direction: Southbound
Stream: On-ramp
From/At: PORT SEVERN ROAD Southbound
To:
Lanes Affected: ALL LANES CLOSED
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Maintenance
Event Start: October 02, 2016 22:00
Event End: October 07, 2016 06:00
Last Change: Entered 2016-09-28 14:47
Last Updated: September 28, 2016 14:47

Top of page Top of page


HWY 89 Eastbound [ NOTTAWASAGA INN - SIMCOE COUNTY ROAD 56 ] - Recurring-Construction
Event Id: 63576
Highway: HWY 89
Direction: Eastbound
Stream:
From/At: NOTTAWASAGA INN
To: SIMCOE COUNTY ROAD 56
Lanes Affected: 1 Right Lane(s)
Comment :
Traffic Impact :
Type - Reason Planned - Recurring-Construction
Event Start: September 27, 2016 20:00
Event End: October 04, 2016 05:00
Last Change: Entered 2016-09-23 09:02
Last Updated: September 23, 2016 09:02

Top of page Top of page


This information is provided as a public service. Although we endeavour to ensure that the information is as current and accurate as possible, errors do occasionally occur. Therefore, we cannot guarantee the accuracy of the information. Readers should, where possible, verify the information before relying on it.